Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Some of the main inputs to rough-cut capacity plan (RCCP) include: bill of resou

ID: 376685 • Letter: S

Question

Some of the main inputs to rough-cut capacity plan (RCCP) include:

bill of resources, bill of materials, master demand schedule, and accounting/finance.

bill of resources, bill of materials, material requirements plan, and accounting/finance.

bill of resources, bill of materials, master demand schedule, and inventory item attributes.

bill of resources, bill of materials, material requirements plan, and supply chain bill.

all of the above is true.

a.

bill of resources, bill of materials, master demand schedule, and accounting/finance.

b.

bill of resources, bill of materials, material requirements plan, and accounting/finance.

c.

bill of resources, bill of materials, master demand schedule, and inventory item attributes.

d.

bill of resources, bill of materials, material requirements plan, and supply chain bill.

e.

all of the above is true.

Explanation / Answer

The answer should be

b. bill of resources, bill of materials, material requirements plan, and accounting/finance.

Because in RCCP company need to plan everything in advance whether the there finance or raw material requirement. Everything needs to be planned.