Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following 5 overhaul jobs are waiting to be processed at Avianic\'s Engine R

ID: 377566 • Letter: T

Question

The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days.

103 205 309 412 517 Calculate the Critical Ratios (CR): (Enter all responsesThe following 5 overhaul jobs are waiting to be processed rounded to two decimal places.) at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days CR Job 103 Duration (days) Job 103 205 309 412 517 Due Date 217 219 218 214 223 15 10 Assume that all jobs arrived on day 180; today's date is 200

Explanation / Answer

critical ratio = (Due Date - Today's date) / processing time

Using the above formula the critical ratio for each job are calculated below :