Show me the solution in steps. I will not accepted the answer if you didn\'t sho
ID: 378731 • Letter: S
Question
Show me the solution in steps. I will not accepted the answer if you didn't show me your work "IN STEPS!". Thank you.
Problem 2, (6%) The Bi-Product Company makes products A and B. Product A takes one half hour to assemble plus one hour of welding time for the parts. Product B requires one hour of assembly and two hours of welding. Given the MPS below, which of the following statement is true? Period Product A 250 400 300 700 Product B 480 450 150 700 a. the capacity requirements for welding in period 1 is 1200 b. the capacity requirements for welding in period 2 is 1200 c. the capacity requirements for assembly in period 1 is 650 d. the capacity requirements for assembly in period 2 is 650Explanation / Answer
Assembly time - Product A = 0.5 hrs
Welding time - Product A = 1 hr
Period 1 - Product A = 250.
Number of assembly hours = 250*0.5 = 125
Number of welding hours = 250*1 = 250
Period 2 - Product A = 400
Number of assembly hours = 400*0.5 = 200
Number of welding hours = 400*1 = 400
Assembly time - Product B = 1 hr
Welding time - Product A = 2 hrs
Period 1 - Product B = 480
Number of assembly hours = 480*1 = 480
Number of welding hours = 480*2 = 960
Period 2 - Product B = 450
Number of assembly hours = 450*1 = 450
Number of welding hours = 450*2 = 900
Hence, the answer is d) The capacity requirements for assembly in period 2 is 650
Period 1 Period 2 Product A - Assembly 125 200 Product A - Welding 250 400 Product B - Assembly 480 450 Product B - Welding 960 900