Question
question 15
The following activities are required to complete a project assigned to you by your boss. Activity Normal Time (days) Immediate Predecessor(s) Crash Cost/ day Max. time reduction $300 5800 $400 S1200 $600 $1400 $100 1800 S1100 3 days 2 days 2 days 1 day 2 days D* A, B D.E 2 days 1 day I day 14 Note: the starred letter will be referred to in a later question. Below is the network diagram for this project. Please answer the following questions based on this project. List the paths of the project and calculate the length of each path.
Explanation / Answer
The S and F at the beginig and end of every path are the Start and Finish activities respectively
Path Length SADGF 11 SADFIF 17 SBDGF 15 SBDFIF 21 SCEFIF 23 SCHF 22