8. Analyzing the critical path of a project provides which benefit? A. Identifie
ID: 378884 • Letter: 8
Question
8. Analyzing the critical path of a project provides which benefit? A. Identifies the fastest path to complete the project B. Displays work in a horizontal bar graph C. Identifies tasks for the work breakdown structure D. Prioritizes which activities to more closely manage
9. Using the critical path method for project management, the critical path should have… A. The most slack of any path in the project B. At least one unit (day/week/month etc.) of slack C. Zero slack D. Not enough information to finish the statement
Explanation / Answer
8. The correct options is C) Identifies tasks for the work breakdown structure
The Critical Path analysis helps in identifying the most important activities, which can impact the project schedule.
9. The correct option is C) Zero Slack
Critical Path is the longest list of sequenced activities that must occur on a project prior to it being complete. These activities have no float or slack time. This means if an activity that is on the critical path takes longer than expected then it will cause a delay in the delivery of the project.