Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 12-3 The following table lists the components needed to assemble an end

ID: 379007 • Letter: P

Question

Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks). and quantities on hand. adAmount Tine on Hand Direct (2)· 3(1), K(3) B(2), J(3) G (2), B(2) H(4), B(2) End 10 15 31 a. If 43 units of the end item are to be assembled. how many additional units of B are needed? (Hint You don't need to develop an 516 0 b. An order for the end item is scheduled to be shipped at the start of week 8. What is the latest week that the order can be started and still be ready to ship on time? (Hint You don't need to develop an MRP plan) -i-L- 2) The latest week

Explanation / Answer

The first answer

Units of B needed per unit

4+2+6= 12

Total B units needed for 43 units

43x12 = 516

Since we already have 28 units on hand, balance units needed

= 516-28 =488