Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Can someone please go through the steps and explain to how to do this problem? I

ID: 381894 • Letter: C

Question

Can someone please go through the steps and explain to how to do this problem? I already have the answer, I just don't know how to do the problem.

A firm has 56 units of product X on hand. Forecasts of demand are 20 units per week and the customer order information is given below. Determine MPS schedule with a lot size of 50. The MPS rule is to schedule production when net inventory before production is less than 10.

                   Week#

Beg. Inv   _____

1

2

3

4

5

Forecast

20

20

20

20

20

Customer Orders

(Committed)

24

18

15

30

15

Requirements

Net Inv. Before MPS

MPS ( _____ )

Projected Inventory

Available-to-Promise Inventory (ATP)

                   Week#

Beg. Inv   _____

1

2

3

4

5

Forecast

20

20

20

20

20

Customer Orders

(Committed)

24

18

15

30

15

Requirements

Net Inv. Before MPS

MPS ( _____ )

Projected Inventory

Available-to-Promise Inventory (ATP)

Explanation / Answer

Requirement = Max(Forecast,Customer orders)

Net inventory before MPS = Previous period project inventory + Beginning inventory

ATP = MPS - next week commited orders - current week committed orders

For week 1 while calculating ATP, instead of MPS, beginning inventory will be considered

So, ATP of Week 1 = 56-24-18 = 14

Projected inventory = Net inventory before MPS - Requirement + MPS

Requirement = Max(Forecast,Customer orders)

Net inventory before MPS = Previous period project inventory + Beginning inventory

MPS is done when Net inventory before MPS - Requirement < 10

ATP = MPS - next week commited orders - current week committed orders

For week 1 while calculating ATP, instead of MPS, beginning inventory will be considered

So, ATP of Week 1 = 56-24-18 = 14

Beg. Inv   56 1 2 3 4 Forecast 20 20 20 20 20 Customer Orders 24 18 15 30 15 (Committed) Requirements 24 20 20 30 20 Net Inv. Before MPS 56 32 12 42 12 MPS ( 50 ) 0 0 50 0 50 Projected Inventory 32 12 42 12 42 14 0 Available-to-Promise Inventory (ATP) 5 0 35