The computation of the duration of the network after ail logic is completed and
ID: 3835094 • Letter: T
Question
The computation of the duration of the network after ail logic is completed and all time estimates are included in the schedule requires a forward and backward pass (computation). These two functions results in sorting all activities into a forward group and a backward group generating the float (slack) on each activity and identifying the critical path generating a new logic for the schedule if it exceeds the desired time duration separating the critical path from the non-critical path activities in the networkExplanation / Answer
The computation of the duration of the networkafter all logic is completed and all time estimates are includedin the schedule requiresa forward and backward pass(computation). These two functions results in
Answer: generating the float (slack) on each activity and identifying the critical path