Microsoft Project Schedule 2 Create a schedule using Microsoft Project and answe
ID: 3886826 • Letter: M
Question
Microsoft Project Schedule 2 Create a schedule using Microsoft Project and answer the questions provided in the exam. Create a schedule using the list of activities below with a start date of October 3, 2016 and including key California state holidays Duration Predecessors Notes Task Description |Notice to Proceed ID 0 days 5 days 3 Remove existing pavement 6 days | 2 Mobilization 4 Remove existing concrete 5 34 Demolition Remove existing subgrade 6 Replace unsuitable base 3 days 8 days new subgrade 4 days 8 Install new curb and guter6 days 7 days 2 days 3 days 2 days 3 days 3 days 0 days Reconstruction 10 install new traffic signais Reconstruction 11 Install new signage 12 13 14 15 Project Completion 12 13 14 . Navigate to the "Resource Sheet and add the following resources o Create the following work resources: i. Excavator@$129hr (Std.) ii. Grader@$103hr (Std.) ili. Scraper$115/hr (Std.) iv. Bulldozer@$83/hr (Std.) MacBook Pro a Search SafeFinderExplanation / Answer
Ans 1. Part a) 11/29/2016 is correct.
Ans 2. Part b) $ 151800 is correct.
Ans 3. Part a) $ 45897 is correct.
Ans 4. Part b) $ 50272 is correct.
Ans 5. Bulldozer, Bottom Dump Truck and Scraper.
Ans 6. Part c) Buy a new piece of equipment.
Ans 7. Part d) Replace unsuitable base material.
Ans 8. Part c) Paving Operations.
Ans 9. Part a) Remove existing pavements.
Ans 10. Part b) 50