Based on the Work Breakdown Structure below please provide a matrix showing the
ID: 396996 • Letter: B
Question
Based on the Work Breakdown Structure below please provide a matrix showing the following:
1. Risk identification
2. Risk assessment
3. Risk response
Work Breakdown Indentured List
WBS
#
Description
Responsible Deliverables
1.0
1.1
1.2
1.3
Requirements
Set weekend for move
Determine move budget
Contract movers
Lewis Make proper arrangements for move
Lewis Determine the avail. Monetary amount
Lewis Ensure required staff is contracted
2.0
2.1
2.2
2.3
Packaging Materials
Order & purchase packaging materials
Print box & personal belonging labels
Box up all items
Lewis Ensure the required packaging materials
Readily available
Lewis Easily identify boxed items
Lewis Prepare furniture & items to be shipped
3.0
3.1
3.2
3.3
3.4
3.5
3.6
Transit
Reserve moving trucks
Load up truck # 1 with boxes, paperwork, and office inventory
Load truck # 2 with office furniture
Block & brace items
Prepare for transit
Cover gasoline / tollway costs
Julia Ensure the correct sized vehicle/s are avail
Lewis Allows for easy loading/unloading
Lewis Allows for furniture to be easily arranged
Lewis Ensure no items shift in transit
Julia Make sure trucks are loaded and in
working conditions
Julia Prepay for additional savings
4.0
4.1
4.2
4.3
Utilities
Arrange installation of phone, fax, security & internet lines at new location
Transfer electrical, water, and
gas bills to new location
Change locks
Steven Required office resources
Julia Required office resources
Julia Ensure added safety at new location
5.0
5.1
5.2
5.3
5.4
The move
Make two-hour transit MIL-ORD
Arrival at new building
Begin unloading truck # 2
Begin unloading truck # 1
Lewis Supervise everything is running
smoothly
Lewis ---
Lewis Offload & set up furniture
Lewis Offload and set up personal belongings
6.0
6.1
6.2
6.3
Misc.
Test phone, fax, & internet lines
Discard packaging materials
Return moving trucks
Steven Ensure operations are ready for business
Julia Get office organized and tidy
Julia Terminate truck rental
WBS
#
Description
Responsible Deliverables
1.0
1.1
1.2
1.3
Requirements
Set weekend for move
Determine move budget
Contract movers
Lewis Make proper arrangements for move
Lewis Determine the avail. Monetary amount
Lewis Ensure required staff is contracted
2.0
2.1
2.2
2.3
Packaging Materials
Order & purchase packaging materials
Print box & personal belonging labels
Box up all items
Lewis Ensure the required packaging materials
Readily available
Lewis Easily identify boxed items
Lewis Prepare furniture & items to be shipped
3.0
3.1
3.2
3.3
3.4
3.5
3.6
Transit
Reserve moving trucks
Load up truck # 1 with boxes, paperwork, and office inventory
Load truck # 2 with office furniture
Block & brace items
Prepare for transit
Cover gasoline / tollway costs
Julia Ensure the correct sized vehicle/s are avail
Lewis Allows for easy loading/unloading
Lewis Allows for furniture to be easily arranged
Lewis Ensure no items shift in transit
Julia Make sure trucks are loaded and in
working conditions
Julia Prepay for additional savings
4.0
4.1
4.2
4.3
Utilities
Arrange installation of phone, fax, security & internet lines at new location
Transfer electrical, water, and
gas bills to new location
Change locks
Steven Required office resources
Julia Required office resources
Julia Ensure added safety at new location
5.0
5.1
5.2
5.3
5.4
The move
Make two-hour transit MIL-ORD
Arrival at new building
Begin unloading truck # 2
Begin unloading truck # 1
Lewis Supervise everything is running
smoothly
Lewis ---
Lewis Offload & set up furniture
Lewis Offload and set up personal belongings
6.0
6.1
6.2
6.3
Misc.
Test phone, fax, & internet lines
Discard packaging materials
Return moving trucks
Steven Ensure operations are ready for business
Julia Get office organized and tidy
Julia Terminate truck rental
Explanation / Answer
1.1 set weekend for move
Identifiable risk is to ensure that accommodation at the other end is ready for occupancy and all required handing over of present accommodation is completed. All scheduled work for the move will be completed by the set weekend and no other appointments exist.
All the identified risks are low. Alternative temporary accommodation can be arranged for as a standby. All handing over and moving tasks need to be scheduled for at least three days prior to the weekend to have a buffer. Similarly scheduled work appointments need to be completed three days prior.
1.2 determine move budget. risk involved is of the planned expenditure going over budget.
The risk is medium and the plan needs to be drawn out allocating required amount for every job associated with the move. This can be handled by allocation of a 15% reserve amount for unforeseen expenditure, and by trying to get accurate quotations for all jobs involved.
1.3 contract movers the risk involved is medium as suitable movers able to perform the required job at the exact time may not be available.
the risk can be managed by obtaining request for proposal from numerous contract homework and selecting the one closest to the budget and available on the required dates, provides insurance for the goods and also provides staff for loading and unloading the trucks. As it is essential that the Movers be dependable any excess amount charged needs to be adjusted from the Reserve. If insurance is not provided it may have to be arranged from an independent insurance and same may need to be done for loading staff and subsequently unloading staff at destination.
2.1 order and purchase packaging materials. Low risk. The risk involved maybe that the ordered packaging materials do not arrive in time. This can be covered by ordering from a site which accepts returns so that packaging material can alternately be purchased personally from a store, immediately if required.
2.2 print box and personal belonging labels. Low risk. The printer may run out of ink or labels material not available. Check that the printer has sufficient in and labelling material is available for performing the task before hand and order the same if required. Alternatively, search risk can be covered by printing the labels from an external source in an emergency.
2.3 box up all items. Medium risk. as extensive packing has to be done in an organised manner. It is essential to draw out an exhaustive list of all the belongings to be boxed along with the order and grouping to be followed. This will require analysis of closely placed items to facilitate easier and quicker packing. Items maybe left out after boxing is completed. This can be managed by contingent plan of taking each item of the list and identifying which box it has gone into before sealing the boxes.
3.1 reserve moving trucks. It is low risk as it is mostly covered in the agreement with the contract movers. As different people are responsible for contracting the Movers and reserving the tracks cooperation and coordination is to be ensured to avoid confusion. The risk can be mitigated by clear communication between Lewis and Julia. Julia needs to be informed about the size of trucks required so she can confirm with the contract movers that the trucks will be of the required size. Ensure that the size of drugs is mentioned in the contract with the movers so they are bound to provide the correct size or abstain from charging extra for larger trucks.
3.2 Load truck number one with boxes. Low risk. Risk maybe of the correct boxes reserved for particular track to ensure the Right Fit may not be loaded. The boxes should be numbered exactly as per sequence of loading along with making sure that the size and weight of the boxes is accounted for while drawing up the plan.
3.3 paper work and office inventory Low risk. Ensure all paper work is completed and office inventory taken. Paperwork may not be complete and office inventory list not prepared. This can be managed by ensuring call office paperwork and inventory for packaging is performed at the same time as the home. Suitably grouping tasks makes them easier to perform and saves lot of time. Considering that both are being handled by Lewis, it is easy to manage this.
3.4 Load Truck number two with office furniture. Low risk. As furniture is a large item the risk of an item being left is difficult. A list office inventory including all furniture is to be made. The furniture is to be numbered for sequence to be followed for loading to ensure that which can be easily arranged optimal utilisation of space and minimal damages.
3.5 block and brace items. Low risk. As this is a task which can be completed on the spot risk and immediately be controlled and mitigated by rearrangement if required to ensure that no items shift in transit resulting in damages. Earlier the best arrangement has already been planned.
3.6 prepare for transit make sure that the trucks are loaded and in working condition comes and the contractual obligations of the movers and is a low risk item as it is easy to manage risk by providing for damages within the contract.