Can someone provide information on how to do this You will use the following inf
ID: 398999 • Letter: C
Question
Can someone provide information on how to do this
You will use the following information for the next four questions E Calendar 1/2013 WN Mo Tu We Th Fr Sa Su 39 23 24 25 26 27 28 29 40 30 1 2 3 4 56 o 417 8 9 10 11 12 13 c 4214 15 16 17 18 19 20 N 43 21 22 23 24 25 26 27 44 28 29 30 31 12 3 45 4 5 6 7 8 9 10 5 46 11 12 13 14 15 16 17 47 18 19 20 21 22 23 24 48 25 26 27 [28 29 30 1 49 2 3 4 5 6 78 .GR processing time 2 days in-house production time 4 days opening period 5 days If a dependent requirement exists with a requirement date of 12/3/2013, MRP will generate an order with what due date? (Enter answer as MM/DD/YYYY)Explanation / Answer
In basic date calculation ( order start date/ order finish date ) the system makes calculations on the basis of backward scheduling.
1. From the date of requirement provided the system subtracts the GR processing time for the calculation of the order finish date.
2. From the order finish date thus arrived at, the system subtracts the inhouse production time to arrive at the order start date.
3. The order start date thus arrived at is utilized by the system for calculation of the order opening date by subtracting the opening period given in scheduling margin key.
Therefore Order Finish date=12/03/2013 less GR processing time 2 days=12/01/2013