Could someone explain the method for doing late start and late finishes? I was d
ID: 414328 • Letter: C
Question
Could someone explain the method for doing late start and late finishes? I was doing good until I got to D. Now how I found the others was wrong for D. I need to know the slack time for all of them.
toger inde is develop ng a progre in su p y chain management certifat on or managers. Ginde has listed and times appear in the accompanying table number o act it s that must be com ered bet re a training pro am o ths nature could b conducted The actr ties. Immediate predecessors Activity Immediate Predecessors) Time (days) A D E, F This exercise contains only parts b, c and d b The cntical actvities tor the leadership training program devclopment prcject are A E-G c)The project length for the leadership training program development project 25 days d) Slack tirie for each of the activities is, Activity Slack TimeExplanation / Answer
The precedence diagram for the activities as follows :
A
B
C
D
F
E
G
The parallel paths and their corresponding durations as follows :
A-E-G = 10 + 5 + 10 = 25 days
B-D-E-G = 5 + 2 + 5 + 10 = 22 days
C-F-G = 3 + 5 + 10 = 18 days
Out of above , A-E-G has the longest duration and hence forms the critical path .
Since duration of critical is same as project duration, it is concluded that project duration is 25 days
Slack for activities B and D = Duration of A-E-G – Duration of B-D-E-G = 25 – 22 = 3 days
Slack for activities C and F = Duration of A-E-G – Duration of C-F-G = 25 – 18 = 7 days
Slack for activities on critical path are always ZERO.
Therefore, slack for activities A, E, G = 0
ACTIVITY
SLACK TIME ( DAYS )
A
0
B
3
C
7
D
3
E
0
F
7
G
0