Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

All of the following statements about a WBS or project network are correct EXCEP

ID: 418303 • Letter: A

Question

All of the following statements about a WBS or project network are correct EXCEPT Help Save &Exit; S The wes sets all project work, resource needs, and budgets into a sequential time frame. O The WBS provides a framework for tracking costs to deliverables and organization units responsible. O The network provides a project schedule by identifying sequential dependencies and timing of project activities. O The wBS is hierarchical while the project network is sequential O The WBS is used to identify eac accomplishment within budget and within a time duration. amom mwm recomrtie oes

Explanation / Answer

All of the following statements about wbs are project network are correct except

The network provides a project schedule by identifying sequence and dependencies and timing of project activities