In earned value analysis: A. it is desirable to have negative variances for both
ID: 418562 • Letter: I
Question
In earned value analysis:
A. it is desirable to have negative variances for both schedule and spending.
B. it is desirable to have positive variances for both schedule and spending.
C. the schedule variance should be positive and the spending variance negative.
D. the schedule variance should be negative and the spending variance positive.
A. it is desirable to have negative variances for both schedule and spending.
B. it is desirable to have positive variances for both schedule and spending.
C. the schedule variance should be positive and the spending variance negative.
D. the schedule variance should be negative and the spending variance positive.
Explanation / Answer
B. it is desirable to have positive variances for both schedule and spending.
Positive Schedule variance means that the project is ahead of the schedule and positive spending variance will mean that the project is withhin the estimated budget.