Problem 13-17 (Algorithmic) Hemmingway, Inc., is considering a $4 million resear
ID: 418777 • Letter: P
Question
Problem 13-17 (Algorithmic)
Hemmingway, Inc., is considering a $4 million research and development (R&D) project. Profit projections appear promising, but Hemmingway's president is concerned because the probability that the R&D project will be successful is only 0.50. Furthermore, the president knows that even if the project is successful, it will require that the company build a new production facility at a cost of $15 million in order to manufacture the product. If the facility is built, uncertainty remains about the demand and thus uncertainty about the profit that will be realized. Another option is that if the R&D project is successful, the company could sell the rights to the product for an estimated $25 million. Under this option, the company would not build the $15 million production facility.
The decision tree is shown in Figure 13.18. The profit projection for each outcome is shown at the end of the branches. For example, the revenue projection for the high demand outcome is $55 million. However, the cost of the R&D project ($4 million) and the cost of the production facility ($15 million) show the profit of this outcome to be $55 ? $4 ? $15 = $36 million. Branch probabilities are also shown for the chance events.
Analyze the decision tree to determine whether the company should undertake the R&D project. If it does, and if the R&D project is successful, what should the company do?
What is the expected value of your strategy? If required, round your answer to 2 decimal places.
Expected value = $ M
What must the selling price be for the company to consider selling the rights to the product? If required, round your answers to 2 decimal places.
Payoff for sell rights would have to be $ M or more. In order to recover the $4M R&D cost, the selling price would have to be $ M or more.
Develop a risk profile for the optimal strategy. If required, round your answers to two decimal places.
Possible Profit Associated Probability $36M $16M $6M -$4M FIGURE 13.1 DECISION TREE FO R HEMMINGWAY, INC Profit (S millions) High Demand 36 0.5 Building Facility ($15 Medium Demand 16 0.3 Low Demand 0.2 Successful 0.5 Start R&D; Project ($4million) 21 Not Successful -4 0.5 Do Not Start the R&D; Project 0
Explanation / Answer
Expected Value (EV) of node 4 = 0.5*36+0.3*16+0.2*6 = 24
This is more than the EV of sell rights (21)
EV of node 2 = 0.5*24+0.5*(-4) = 10
EV of start R&D project is higher as compared to not starting the project.
Therefore, the company should undertake the R &D project.
Expected Value of this strategy = EV of node 2 = $ 10 M
Profit for sell rights would have to be $ 24 or more (EV of nose 4). In order to recover the $4 M R&D cost, the selling price would have to be $ 28 M or more.
Risk profile
Possible profit Associated Probability $ 36M 0.5*0.5 = 0.25 $ 16M 0.5*0.3 = 0.15 $ 6M 0.5*0.2 = 0.10 - $ 4 0.5