Situation 3: An assembly line operates eight hours a day and requires the follow
ID: 423102 • Letter: S
Question
Situation 3:
An assembly line operates eight hours a day and requires the following tasks (the 'duration' is in seconds). Based on the following information available, answer the following questions (see table above).
A. Determine the minimum number of work stations (with their corresponding tasks) and balance the line to assemble 1,050 products per day.
B. There is a proposal to produce 75 additional products per day. The administration will accept the proposal as long as there is no need to make changes in the number of work stations. Should the company accept the offer? If the answer is no, what maximum amount of products would be viable?
Explanation / Answer
An assembly line operates eight hours a day and requires the following tasks (the 'duration' is in seconds). Based on the following information available, answer the following questions (see table above).
A. Determine the minimum number of work stations (with their corresponding tasks) and balance the line to assemble 1,050 products per day.
B. There is a proposal to produce 75 additional products per day. The administration will accept the proposal as long as there is no need to make changes in the number of work stations. Should the company accept the offer? If the answer is no, what maximum amount of products would be viable?