Mary is planning her wedding and develops the following preliminary information.

ID: 432217 • Letter: M

Question

Mary is planning her wedding and develops the following preliminary information.

A (select wedding date)

None

2 weeks

B (select wedding location)

None

5 weeks

C (guest list, who is attending)

A, B

1 week

D (select entertainment)

B, C

4 weeks

E (choose catering)

A

3 weeks

F (wedding day)

D, E

0 weeks

Choose the correct network for the project.

The correct network is -Select-network Anetwork Bnetwork Cnetwork DItem 1 .

What is the critical path?

The critical path is -Select-A-E-FA-D-E-FB-C-D-FB-D-FA-C-D-FItem 2 .

What is the project completion time? Round your answer to the nearest whole number.

  weeks

What activity has the most slack? Round your answer to the nearest whole number.

Activity -Select-ABCDEFItem 4  with   weeks.

Hide Feedback

Incorrect

Mary is planning her wedding and develops the following preliminary information.

Activity Immediate
Predecessor(s)
Estimated
Normal Time

A (select wedding date)

None

2 weeks

B (select wedding location)

None

5 weeks

C (guest list, who is attending)

A, B

1 week

D (select entertainment)

B, C

4 weeks

E (choose catering)

A

3 weeks

F (wedding day)

D, E

0 weeks

Choose the correct network for the project.

The correct network is -Select-network Anetwork Bnetwork Cnetwork DItem 1 .

A. B. C. D.

What is the critical path?

The critical path is -Select-A-E-FA-D-E-FB-C-D-FB-D-FA-C-D-FItem 2 .

What is the project completion time? Round your answer to the nearest whole number.

  weeks

What activity has the most slack? Round your answer to the nearest whole number.

Activity -Select-ABCDEFItem 4  with   weeks.

Explanation / Answer

The parallel paths and their corresponding durations as follows :

A-E-F = 2 + 3 + 0 = 5 weeks

A-C-D-F = 2 + 1 + 4 + 0 = 7 weeks

B-C-D-F = 5 + 1 + 4 + 0 = 10 weeks

B-D-F = 5 + 4 + 0 = 9 weeks

Since , B-C-D-F has the longest duration , it forms the critical path .Since, project completion time is same as duration of critical path, project completion time is 10 weeks .

CRITICAL PATH = B-S-D-F

PRJECT COMPLETION TIME = 10 WEEKS

Slack of activity A

= Duration B-C-D-F – Duration A-C-D-F

= 10 – 7

= 3 weeks

Slack of activity E

= Duration B-C-D-F – Duration A-E-F

= 10 – 5

= 5 weeks

Therefore, activity E will have maximum slack of 5 weeks

ACTIVITY E WILL HAVE MOST SLACK OF 5 WEEKS

CRITICAL PATH = B-S-D-F

PRJECT COMPLETION TIME = 10 WEEKS