Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following CPM network has estimates of the normal time in weeks listed for t

ID: 435788 • Letter: T

Question

The following CPM network has estimates of the normal time in weeks listed for the activities:

a. Identify the critical path.


b. What is the length of time to complete the project?


Number of weeks            

c. Which activities have slack, and how much?

Here is a table of normal and crash times and costs.


d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion?


d-2. What would be the total incremental cost?


Total incremental cost            $


d-3. Is the critical path changed?

A-C-D-F-G A-C-D-E-G A-B-D-F-G A-B-D-E-G B(4) D(6) F(5) A(7) G(2)) C(2) E(3)

Explanation / Answer

The possible parallel paths and their corresponding durations as follows :

A-B-D-F-G = 7 + 4 + 6 + 5 +2 = 24

A-B-D-E-G = 7 + 4 + 6 + 3 + 2 = 22

A-C-D-F-G = 7 + 2 + 6 + 5 + 2 = 22

A-C-D-E – G = 7 + 2 + 6 + 3 + 2 = 20

Out of the above, ABDBFG has the longest duration and hence forms the critical path .

CRITICAL PATH = A-B-D-F-G

Length of time to complete the project is same as duration of the critical path . Therefore, length of time to complete the project is 24 weeks

LENGTH OF TIME TO COMPLETE THE PROJECT = 24 WEEKS

It is to be noted that all activities lying on critical path have NO slack.

Therefore activities which do not have slack are : A/B/D/F/G

Slack for activity E = Duration A-B-D-F-G – Duration A-B-D-E-G = 24 – 22 = 2 weeks

Slack for activity C = Duration A-B-D-F-G – Duration A-C-D-F-G = 24 – 22 = 2 weeks

SLACK : C , 2 WEEKS AND E , 2 WEEKS

Activities which should be cut to shorten total duration by 2 weeks must be those activities lying on critical path. Therefore, combination of activities which should be crashed/cut must be from A-B-D-F-G

Cost of crashing activity A by 1 day ( 7 to 6 days ) = $9800 - $7500 = $2300

Cost of crashing activity B by 1 day ( 4 days to 3 days ) = $8500 - $6000 = $2500

Cost of crashing activity D by 2 days ( 6 days to 4 days ) = $4800 - $2500 = $2300

Cost of crashing activity F by 1 day ( 5 days to 4 days ) = $7000 - $5200 = $1800

Cost of crashing activity G by 1 day ( 2 days to 1 day ) = $7800 - $4250 = $3550

From the above data , it is thus evident that most ECONOMIC way to cut 2 weeks from the schedule is to crash activity D by 2 days since it is the LEAST COST option.

Th next best option is to choose activity A and F with incremental cost of $2300 + $1800 = $4100 , which is also not given as part of the options

The next best option is to choose activity B and F with incremental cost of $2500 + $1800 = $4300

ACTIVITIES SHOULD BE CHOSEN = B, F

TOTAL INCREMENTAL COST = $4300

WIL THE CRITICAL PATH CHANGE : NO

CRITICAL PATH = A-B-D-F-G