Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The design of a system is to be pursued from one of the available alternatives.

ID: 438636 • Letter: T

Question


The design of a system is to be pursued from one of the available alternatives. Each alternative has a life cycle cost associated with an expected future. The costs for the corresponding futures are given in the following table (in millions of dollars). If the probabilities of occurrence of the futures are 30%, 50% and 20% respectively which alternative is most desirable from an expected cost viewpoint? Assume interest 10%.

Design 1 Years
Future 1 2 3 4 5 6 7 8 9 10 11 12
Optimistic 0.4 0.6 5.0 7.0 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Expected 0.6 0.8 1.0 5.0 10.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Pessimistic 0.8 0.9 1.0 7.0 10.0 1.2 1.2 1.2 1.2 1.2 1.2 1.2

Design 2 Years
Future 1 2 3 4 5 6 7 8 9 10 11 12
Optimistic 0.4 0.4 0.4 1.0 3.0 2.5 2.5 2.5 2.5 2.5 2.5 2.5
Expected 0.6 0.8 1.0 3.0 6.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0
Pessimistic 0.6 0.8 1.0 5.0 6.0 3.1 3.1 3.1 3.1 3.1 3.1 3.1

Explanation / Answer

design 1
Optimistic NPV (millions)= 0.4/1.1 + 0.6/1.12 + ...........+0.8/1.111 + 0.8/1.112

similarily calculate NPV for Expected and pessimistic

now design 1 expected cost= 0.3*(NPV-optimistic) + 0.5*(NPV-Expected)+ 0.2*(NPV-pessimistic)

repeat the same procedure for design 2 and calculate expected cost

which ever is less of the two costs is the choosen alternative

since i dunnot have calculator right now i am only mentioning the procedure. this one is correct procedure