Slack time in a network is the a. shortest amount of time that could be required
ID: 439153 • Letter: S
Question
Slack time in a network is the a. shortest amount of time that could be required to complete the activity. b. amount of time that an activity can be delayed without delaying the entire project. c. amount of time that you would expect it would take to complete the activity. d. amount of time that an activity would take assuming very unfavorable conditions. e. difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.Explanation / Answer
e. difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times.