An analyst has timed a metal-cutting operation for 50 cycles. The average time p

ID: 445851 • Letter: A

Question

An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.4 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 137 percent. Assume an allowance of 15 percent of job time. Find the standard time for this operation.


minutes

An analyst has timed a metal-cutting operation for 50 cycles. The average time per cycle was 10.4 minutes, and the standard deviation was 1.20 minutes for a worker with a performance rating of 137 percent. Assume an allowance of 15 percent of job time. Find the standard time for this operation.

Explanation / Answer

Standard Time =(Observed time X Rating Factor)(1+PFD Allowance)

=(10.4*1.37)(1+.15) = 16.38520 minutes