1-    Consider the following project schedule:

Activity

Immediate

Predecessor

Optimistic

Most probable

Pessimistic

A

--

1

2

3

B

--

2

3

4

C

A

4

5

6

D

B

8

9

10

E

C

2

5

8

F

B

4

5

6

G

E

1

2

3

                                                                                                         

Determine the expected time, earliest time, latest start, finish times and variance for each activity. Also determine the critical path and expected project completion time.

Activity

Immediate

Predecessor

Optimistic

Most probable

Pessimistic

A

--

1

2

3

B

--

2

3

4

C

A

4

5

6

D

B

8

9

10

E

C

2

5

8

F

B

4

5

6

G

E

1

2

3

Explanation / Answer

Activity Optimistic Most Probable Pessimistic Expected Time Variance Predecessor ES EF LS LF Slack A 1 2 3 2.00 0.11 None 0 2.00 0.00 2 0 Critical Path Activity B 2 3 4 3.00 0.11 None 0 3.00 2.00 5 2 C 4 5 6 5.00 0.11 A 2 7.00 2.00 7 0 Critical Path Activity D 8 9 10 9.00 0.11 B 3 12.00 5.00 14 2 E 2 5 8 5.00 1.00 C 7 12.00 7.00 12 0 Critical Path Activity F 4 5 6 5.00 0.11 B 3 8.00 9.00 14 6 G 1 2 3 2.00 0.11 E 12 14.00 12.00 14 0 Critical Path Activity 31.00 1.67 Paths Duration Weeks A-C-E-G 2+5+5+2 14.00 Critical path B-D 3+9 12.00 B-F 3+5 8.00 *Expected = (Optimistic + 4 * Probable + Pessimistic) / 6 Variance = (Pessimistic - Optimistic / 6)^2 Standard Deviation = Variance ES = E of Tail Event EF = ES + Activity Duration LF = L of Head Event LS = LF - Activity Duration Slack - LS - ES E = Earliest occurrence time for the event L = Latest allowable time for the occurrence of event Critical path = A-C-E-G Expected Time = 14 Variance = 1.3333 Standard Deviation = 1.1547 weeks