Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Part 2 Below is the Bill of Materials (BOM) and Master Production Schedule (MPS)

ID: 451407 • Letter: P

Question

Part 2

Below is the Bill of Materials (BOM) and Master Production Schedule (MPS) for a chair. The number in the parenthesis indicates the quantity needed and the lead time is shown in weeks.

Week

1

2

3

4

5

6

7

8

Quantity Needed

0

0

0

35

75

65

80

85

2. Determine the timing of the Planned Receipts and Planned Order Releases for the chairs assuming Scheduled receipts of 20 units in week 2 and 35 units in week 4 and a Projected On-hand Inventory of 20 units. Assume a L4L lot sizing rule with a lead time period of 2 weeks.

Item: Chairs                                                                     Lot Size: L4L

Description:                                                                       Lead Time: 2 week

Week

1

2

3

4

5

6

7

8

Gross Requirements

Scheduled

Receipts

Projected

Available Balance

Net

Requirements

Planned

Receipts

Planned Order

Releases

Determine the timing of the Planned Receipts and Planned Order Releases for the leg assemblies assuming Scheduled receipts of 30 units in week 1 and a Projected On-hand Inventory on 40 units. Assume an Economic Order Quantity lot sizing rule where the EOQ is 100.

Item: Leg Assembly                                                        Lot Size: EOQ = 100

Description:                                                                       Lead Time: 2 week

Week

1

2

3

4

5

6

7

8

Gross Requirements

Scheduled

Receipts

Projected

Available Balance

Net

Requirements

Planned

Receipts

Planned Order

Releases

Week

1

2

3

4

5

6

7

8

Quantity Needed

0

0

0

35

75

65

80

85

Explanation / Answer

Given for item - Chairs, L4L and lead time = 2 weeks

Based on MPS, the gross requirement figures are written

The planned order release for leg assemblies can not be calculated becuase the BOM is not given here.

Weeks 1 2 3 4 5 6 7 8 Gross Requirements 0 0 0 35 75 65 80 85 Scheduled Receipts 20 35 Projected Inventory 20 units 20 40 40 75 40 0 0 0 Net Requirements 0 0 0 0 35 65 80 85 Planned Receipts 0 0 0 0 35 65 80 85 Planned order release 35 65 80 85