Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Prepare a master schedule given this information: It is now the end of week 1; c

ID: 452544 • Letter: P

Question

Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that a production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "0" wherever required.)


June

July

Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that a production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "0" wherever required.)

Explanation / Answer

Master Schedule

Lot Size: 70

Inventory on hand = 64.

June

July

1

2

3

4

5

6

7

8

Forecast

30

30

30

30

40

40

40

40

Customer orders (committed)

33

25

16

11

8

3

0

0

Projected on-hand inventory

31

1

41

11

41

1

31

61

MPS

0

0

70

0

70

0

70

70

ATP

6

0

43

0

59

0

70

70

Table for calculating Projected on-hand inventory and MPS:

Week

Inventory from Earlier Week

Reqmts.

(Greater of Forecast and Customer orders every week)

Net Inventory prior to MPS

MPS

(= 70 units)

Projected on-hand inventory

1

64

33

31

31

2

31

30

1

1

3

1

30

-29

+ 70 =

41

4

41

30

11

11

5

11

40

-29

+ 70 =

41

6

41

40

1

1

7

1

40

-39

+ 70 =

31

8

31

40

-9

+ 70 =

61

Projected on-hand inventory = Inventory from earlier week – Current week’s requirements + MPS.

Projected on-hand inventory for week 1 = 64 – 33 + 0 = 31.

Projected on-hand inventory for week 2 = 31 – 30 + 0 = 1.

Similarly, Projected on-hand inventory is calculated for the remaining weeks.

ATP Calculations:

ATP (using “look-ahead” procedure) for week 1 = On-hand inventory + MPS – (Sum of actual orders) = 64 + 0 – (33 + 25) = 6.

Then we calculate ATP only for those weeks having MPS quantity. i.e., weeks 3, 5, 7 and 8.

After week 1, there is no need of on-hand inventory.

ATP for week 3 = MPS - (Sum of actual orders) = 70 – (16 + 11) = 43.

ATP for week 5 = MPS - (Sum of actual orders) = 70 – (8 + 3) = 59.

ATP for weeks 7 and 8 = MPS quantity = 70 (due to absence of customer order).

Lot Size: 70

Inventory on hand = 64.

June

July

1

2

3

4

5

6

7

8

Forecast

30

30

30

30

40

40

40

40

Customer orders (committed)

33

25

16

11

8

3

0

0

Projected on-hand inventory

31

1

41

11

41

1

31

61

MPS

0

0

70

0

70

0

70

70

ATP

6

0

43

0

59

0

70

70