Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Suppose we had a project with only eight activities, as ilustrated in the next t

ID: 453403 • Letter: S

Question

Suppose we had a project with only eight activities, as ilustrated in the next table. The table also shows our calculated normal activity durations and costs and crashed durations and their costs. As a project manager, you have been asked to do full crashing.

Activity

Normal

Duration                 Cost

Crash

   Duration                Cost

A

5 days

$ 1,000

3 days

$ 1,500

B

7 days

700

6 days

1,000

C

3 days

2,500

2 days

4,000

D

5 days

1,500

5 days

1,500

E

9 days

3,750

6 days

9,000

F

4 days

1,600

3 days

2,500

G

6 days

2,400

4 days

3,000

H

8 days

9,000

5 days

15,000

TOTAL COST=

22,450

$ 37,500

Activity

Normal

Duration                 Cost

Crash

   Duration                Cost

A

5 days

$ 1,000

3 days

$ 1,500

B

7 days

700

6 days

1,000

C

3 days

2,500

2 days

4,000

D

5 days

1,500

5 days

1,500

E

9 days

3,750

6 days

9,000

F

4 days

1,600

3 days

2,500

G

6 days

2,400

4 days

3,000

H

8 days

9,000

5 days

15,000

TOTAL COST=

22,450

$ 37,500

Explanation / Answer

PRecedence relationship between the activities is not provided, in absence of which, network diagram cannot be drawn. however, if all the activities are in series, then the total duration of the project completion time is 47 , and project duration after full crash is 34 and the cost is 37500.