If the project must be completed in 53 days, what would be the total cost of the

ID: 459223 • Letter: I

Question

If the project must be completed in 53 days, what would be the total cost of the project?

A. $193,000

B. $8,000

C. $185,000

D. $2,000

For the crashing data provided, assume steps are taken to complete the project in 52 days, but the manager decides project time must be shortened one more day. Which task(s) must be crashed to lower project time from 52 days to 51 days?

A. Task A 3 days and Task F 3 days

B. Task A 1 Day

C. Task H 2 days

D. Task H 1 day

(untitled) Solution

Project time

Period cost

Cumulative cost

A

B

C

D

E

F

G

H

I

J

K

59

0

0

58

1000

1000

1

57

1000

2000

2

56

1000

3000

3

55

1666.67

4666.67

1

3

54

1666.67

6333.33

2

3

53

1666.67

8000

3

3

52

2000

10000

3

3

1

51

2000

12000

3

3

2

50

3666.67

15666.67

3

1

3

2

49

3666.67

19333.33

3

2

3

2

48

3666.67

23000

3

3

3

2

47

4000

27000

3

3

3

2

1

46

4000

31000

3

3

3

2

1

1

(untitled) Solution

Activity

Normal time

Crash time

Normal Cost

Crash Cost

Crash cost/pd

Crash by

Crashing cost

Project

59

46

A

15

12

15000

20000

1666.67

3

5000

B

9

6

18000

26000

2666.67

0

0

C

13

10

29000

40000

3666.67

3

11000

D

10

8

10000

12000

1000

0

0

E

8

5

20000

30000

3333.33

0

0

F

9

6

12000

15000

1000

3

3000

G

4

1

20000

24000

1333.33

0

0

H

12

10

36000

40000

2000

2

4000

I

10

7

5000

8000

1000

0

0

J

6

5

4000

8000

4000

1

4000

K

4

3

16000

20000

4000

1

4000

TOTALS

185000

31000

(untitled) Solution

Project time

Period cost

Cumulative cost

A

B

C

D

E

F

G

H

I

J

K

59

0

0

58

1000

1000

1

57

1000

2000

2

56

1000

3000

3

55

1666.67

4666.67

1

3

54

1666.67

6333.33

2

3

53

1666.67

8000

3

3

52

2000

10000

3

3

1

51

2000

12000

3

3

2

50

3666.67

15666.67

3

1

3

2

49

3666.67

19333.33

3

2

3

2

48

3666.67

23000

3

3

3

2

47

4000

27000

3

3

3

2

1

46

4000

31000

3

3

3

2

1

1

Explanation / Answer

Let's look into the 2nd table, that gives cost details for the
project. In normal time, project can be completed in 59 days, with a
total cost of 185000. As the requirement in the 1st part is to
complete project in 53 days, project needs to be crashed by 6 days.
Based on cost of crash per day, activities are picked for crashing. In
current case, least cost of crash per day is 1000. Available days in
that category are 3 days, as mentioned in crash days column.

Hence activity F is crashed by 3 days, with an incurring cost of 3*1000 = 3000.

Next least cost of crash is for activity G, with 1333.33 per day, but
there are no days available for crash.

Next least cost of crash is 1666.67 for activity A, with 3 days
available. so cost is 1666.67*3 = 5000.

Hence total 6 days crash costs 3000+5000 = 8000.

Final cost to complete project in 53 days is 185000+8000 = 193000. Option A.

Now, if project has to be completed in 52 days, next activity with
least cost of crash is H, with cost per day as 2000.

hence for project to be completed in 52 days, additional cost of 2000
is incurred means, 193000+2000 = 195000.

For 51 days, it is one more day crash for activity H, means another
2000 additional cost.

Total cost = 195000+2000 = 197000, for 51 day completion.