Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 8-9 An assembly line is to be designed to operate 7 1 / 2 hours per day

ID: 469072 • Letter: P

Question

Problem 8-9

An assembly line is to be designed to operate 71/2 hours per day and supply a steady demand of 300 units per day. Here are the tasks and their performance times:

What is the theoretical minimum number of workstations? (Round up your answer to the next whole number.)

  

Assign tasks to workstations using the longest operating time. (Leave no cells blank - be certain to enter "0" wherever required.)

  

Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 71/2 hours per day. (Round your answers to the nearest whole number.)

An assembly line is to be designed to operate 71/2 hours per day and supply a steady demand of 300 units per day. Here are the tasks and their performance times:

Explanation / Answer

Activity

Predecessor

Duration (week)

a

None

70

b

None

40

c

None

45

d

a

10

e

b

30

f

C

20

g

d

60

h

e

50

i

f

15

j

g

25

k

h, i

20

l

j, k

25

Total Work Time

410

Demand = D =300 units per day

Available hours = 7.5 hours per day
Available time (seconds) = 7.5 x 60 x 60 = 27,000 seconds

Total Work time = 410 seconds

a.

Determine Cycle Time

Cycle time of the Line = Available time (seconds)/Demand

Ct = 27000/300 = 90 seconds

So assembly must be capable of processing units once every 90 seconds.

Cycle time gives idea of how frequently the products are processed by assembly line.

b.

Determine number of workstation required:

Number of workstation required in assembly line depends on the cycle time and total work content that is total amount of time required to produce the product.

So for assembly line number of workstation required is as follows:

Number of workstation = (total work content)/(required cycle time)

Number of workstation required = 410/90 = 4.56

Actual numbers of workstations required are 5 workstations.

Arrange the tasks according to longest tasks first as shown below:

Activity

Predecessor

Duration (week)

a

None

70

g

d

60

h

e

50

c

None

45

b

None

40

e

b

30

j

g

25

l

j, k

25

f

c

20

k

h, i

20

i

f

15

d

a

10

Applying largest candidate rule to balance the line:

Work Elements Assigned to Stations According to the Largest Candidate Rule. For a workstation select tasks with largest duration task such that:

For example workstation #1 consists of task a with duration 70 and task d which required task a to complete with duration 10. Thus the WS #1 cycle time is 80 seconds

Workstation #

Tasks

workstation, Work Time (CW)

Cycle Time (Ct)

Idle = Ct + CW

1

a, d

70+10 = 80

90

10

2

g, j

60+25 = 85

90

5

3

c, b

45+40 = 85

90

5

4

e, h

30+50 = 80

90

10

5

f, i, k, l

20+15+20+25 = 80

90

10

C.

Efficiency of assembly line = Total work time/(no. of workstation x Cycle time)

Efficiency = 410/(5 x 90)

Efficiency = 91.11%

D

Revised Demand = 300 * 1.10 = 330 units

Revised Cycle Time = 27000/330 = 81.82 seconds

As there is no idle time for Workstations #2 and #3, do not reduce the cycle time, instead work overtime.

Overtime production units = Revised demand - Production per day as per CT = 20 sec

Overtime production units = 30 – 300 = 30 units

Overtime (seconds) = 30 units x CT = 30 x 90 = 2700 seconds

Overtime in minutes = 2700/60 = 45 minutes.

Thus, work 45 minutes of overtime

Activity

Predecessor

Duration (week)

a

None

70

b

None

40

c

None

45

d

a

10

e

b

30

f

C

20

g

d

60

h

e

50

i

f

15

j

g

25

k

h, i

20

l

j, k

25

Total Work Time

410