Complete the following MRP matrix for Item X. Determine when orders should be re

ID: 472234 • Letter: C

Question

Complete the following MRP matrix for Item X. Determine when orders should be released and the size of those orders.

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

25

30

56

25

100

40

30

20

Scheduled Receipts

50

Projected on Hand

30

Net Requirements

Planned Order Receipts

Planned Order Releases

Release orders in periods 1 through 5 for quantities of 50, 50, 56, 50, and 50 respectively.

Please, do not post the same chart that has been floating around this site. It hardly answers the question.

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

25

30

56

25

100

40

30

20

Scheduled Receipts

50

Projected on Hand

30

Net Requirements

Planned Order Receipts

Planned Order Releases

Explanation / Answer

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

25

30

56

25

100

40

30

20

Scheduled Receipts

50

Projected on Hand

30

5

25

19

44

0

10

30

10

Net Requirements

31

6

56

40

20

Planned Order Receipts

50

50

56

50

50

Planned Order Releases

50

50

56

50

50

Period-1

Project at hand =30-25=5

Period-2

Project at hand =50+5-30=25

Period -3

Net requirement =56-25=31

Planned order receipt=50(Min lot size)

Project at hand=50-31=19

Period-4

Net requirement =25-19=6

Planned order receipt=50(Min lot size)

Project at hand=50-6=44

Period-5

Net requirement =100-44=56

Planned order receipt=56(more than Min lot size of 50)

Project at hand=56-56=0

Period-6

Net requirement =40-0=40

Planned order receipt=50(Min lot size)

Project at hand=50-40=10

Period-7

Net requirement =30-10=20

Planned order receipt=50(Min lot size)

Project at hand=50-20=30

Period-8

Net requirement =20

Project at hand=30-20=10

Planned Order Releases is two period lag with Planned Order Receipts

Item: X

LLC: 0

Period

Lot Size: Min 50

LT: 2

1

2

3

4

5

6

7

8

Gross Requirements

25

30

56

25

100

40

30

20

Scheduled Receipts

50

Projected on Hand

30

5

25

19

44

0

10

30

10

Net Requirements

31

6

56

40

20

Planned Order Receipts

50

50

56

50

50

Planned Order Releases

50

50

56

50

50