QUESTION 1: Subcontract agreements include ____ clauses that “hold the contracto
ID: 1710806 • Letter: Q
Question
QUESTION 1:
Subcontract agreements include ____ clauses that “hold the contractor harmless” from actions of the subcontractor.
indemnification
termination
acceptability
scope of work
QUESTION 2:
Who developed the concept of total quality management?
OSHA
Dr. Edwards Deming
Dr. Phillip Brians
American Society for Testing and Materials
QUESTION 3:
The quality management program uses a continuous “____” methodology.
Do–Plan-Check–Act
Check-Plan–Do-Act
Plan–Do–Check–Act
Plan-Check-Do-Act
QUESTION 4:
Most subcontract agreements have a “____ clause,” which provides that the subcontractor will be paid after the contractor receives payment from the project owner, payments for the work, less the amount held for retainage, are normally received over 90 days after the work is performed.
scope of work
contingent payment
indemnification
retroactive application
Explanation / Answer
2) edwards deming developed the concept of total quality management.
he is an american . some other americans also developed total quality management.deming is one of them.
3) plan - do -check-act is the concept.
firstly we have to plan the program.
we have to work on that plan .it is doing.
after doing the program we have to check it to rectify the mistakes.
finally we have to implement that.