QUESTION 35 14.00000 poi 35. The We-Grew-it Cooperative employs week (9 weeks) D

ID: 1838991 • Letter: Q

Question

QUESTION 35 14.00000 poi 35. The We-Grew-it Cooperative employs week (9 weeks) Duning that time, the following incidents occurred 30 full-time workers during the harvest season. Last fall during the months of October and November workers averaged 55 hours per Andy Alcorn had his am cut when he fell against a steel support. He drove to the emergency room where he received 8 stitches and a tetanus shot. He was told to keep the wound clean for at least 4 days and was moved to an office job for that time. He returned to work the same day 2 Bob Brown had his foot run over by a fork truck. He had 2 small bones broken in his foot and ended up in a walking cast. He missed 3 days of work, then returned to 3. Chuck Casey's shirt was caught in a grain auger and ripped off him. He was uninjured, but went to the coffee shop for an hour to settle his nerves before returning to 4 Dan Drake fell from the loading dock and knocked himself out. He was unconscious for 5 minutes and was diagnosed at the hospital with a mild concussion. He his regular job work missed work the next day with a severe headache resulting from the concussion 5. Emily Eaves left the office one evening and stopped to buy groceries. She shut the car door on her finger and broke her little finger. She missed two days of work Caiculate the total manhours worked (4 points), the OSHA incidence Rate ( 4 points) the Severity Rate (4 points) and the average severity (2 points) TTT ? Paragraph ? Anal 3(12pt} ?·E·T. ? Click Save and Submit to save and submit.Click Save All Answers to save all ansuers US 6

Explanation / Answer

Given 30 full-time workers and each worked for an average of 55 hours per week for the 9 week period.

Hence the no. of hours worked for a 9 week period = 55*9 = 495 hours

Total manhours worked = 495*26+(495-3*24)+(495-1)+(495-1*24)+(495-2*24) = 14705

OSHA Incidence rate = No. of recordable cases*200000/no. of labour hours = 5*200000/14705 = 68.00

Severity rate = Total no. of lost workdays/total no. of recordable incidents = (3+1/24+1+2)/5 =1.21

Average severity = Total amount of losses insurance compancy experiences/total no. of claims that were made against policies that it underwrites