Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 17-7A Owen Company manufactures bicycles and tricycles. For both product

ID: 2336219 • Letter: P

Question

Problem 17-7A

Owen Company manufactures bicycles and tricycles. For both products, materials are added at the beginning of the production process, and conversion costs are incurred uniformly. Owen Company uses the FIFO method to compute equivalent units. Production and cost data for the month of March are as follows.

Production Data—Bicycles Units Percentage Complete Work in process units, March 1 190 80 % Units started into production 1,400 Work in process units, March 31 310 40 %

Cost Data—Bicycles Work in process units, March 1 $19,330 Direct materials 50,000 Direct labor 26,500 Manufacturing overhead 29,900

Production Data—Tricycles Units Percentage Complete Work in process units, March 1 140 75 % Units started into production 1,000 Work in process units, March 31 60 25 %

Cost Data—Tricycles Work in process units, March 1 $6,050 Direct materials 30,400 Direct labor 14,200 Manufacturing overhead 19,800

1. Calculate the equivalent units of production for materials and conversion costs for both the bicycles and the tricycles.

2. Calculate the unit costs of production for materials and conversion costs for both the bicycles and the tricycles.

3. Calculate the assignment of costs to units transferred out and in process at the end of the accounting period for both the bicycles and the tricycles.

4. Prepare a production cost report for the month of March for the bicycles only

Explanation / Answer

Answer 1

Particular

Material

Conversion

Equivalent Units Bycycle

1590

1442

Equivalent Units Tricycle

1140

1130

Answer 2

Particular

Material

Conversion

Bycycle

31.4

39.1

TriCycles

26.67

30.09

Answer 3

Bycycle

Tricycle

Units

Cost

Units

Cost

Completed

1280

109645.4

1080

67345.58

WIP 31 March

310

14598.4

60

2051.36

Workings:-

Bicycles

March 1 WIP (1)

190

Unit started (2)

1400

March 31 WIP (3)

310

Unit Started and completed (1+2-3)

1280

Material

Conversion

Units (1)

% completed

% completion in March (2)

Equivelent Units (1*2)

Units (1)

% completed

% completion in March (2)

Equivelent Units (1*2)

March 1 WIP

190

100%

0%

0

190

80%

20%

38

Unit started and completed

1280

0%

100%

1280

1280

0%

100%

1280

March 31 WIP

310

0%

100%

310

310

0%

40%

124

1590

1442

Cost

Material

Direct Labour

Mfg Overhead

Total

During the month (1)

50000

26500

29900

Equivalent Units (2)

1590

1442

1442

Per Unit (3)=(1/2)

31.4

18.4

20.7

Unit transfered (4)

1280.0

1280.0

1280.0

Cost of unit Transffered (5)=(3)*(4)

40251.6

23522.9

26540.9

90315.4

Openin WIP cost (6)

19330

Total cost of unit Transfered (7)=(5+6)

109645.4

Equivalent Unit in WIP March 31 (8)

310.0

124.0

124.0

Closing WIP cost (3*8)

9748.4

2278.8

2571.2

14598.4

Tricycles

March 1 WIP (1)

140

Unit started (2)

1000

March 31 WIP (3)

60

Unit Started and completed (1+2-3)

1080

Material

Conversion

Units (1)

% completed

% completion in March (2)

Equivelent Units (1*2)

Units (1)

% completed

% completion in March (2)

Equivelent Units (1*2)

March 1 WIP

140

100%

0%

0

140

75%

25%

35

Unit started and completed

1080

0%

100%

1080

1080

0%

100%

1080

March 31 WIP

60

0%

100%

60

60

0%

25%

15

1140

1130

Cost

Material

Direct Labour

Mfg Overhead

Total

During the month (1)

30400

14200

19800

Equivalent Units (2)

1140

1130

1130

Per Unit (3)=(1/2)

26.6667

12.56637168

17.52212389

Unit transfered (4)

1080

1080

1080

Cost of unit Transffered (5)=(3)*(4)

28800

13571.68142

18923.89381

61295.57522

Openin WIP cost (6)

6050

Total cost of unit Transfered (7)=(5+6)

67345.57522

Equivalent Unit in WIP March 31 (8)

60

15

15

Closing WIP cost (3*8)

1600

188.4955752

262.8318584

2051.327434

Particular

Material

Conversion

Equivalent Units Bycycle

1590

1442

Equivalent Units Tricycle

1140

1130