Beavis Construction Company was the low bidder on a construction project to buil

ID: 2348560 • Letter: B

Question

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below: Cost incurred during the year 2012 - $450,000 Cost incurred during the year 2013 - $1,100,000 Estimated cost to comple 2012 - $1,050,000 Estimated cost to comple 2013 - $0 Billing during the year 2012 - $400,000 Billing during the year 2013 - $1,400,000 Cash collected during the year 2012 - $300,000 Cash collected during the year 2013 - $1,500,000 Assume that Beavis uses the percentage-of-completion method for revenue recognition. Required: Compute the amount of gross profit recognized during 2012 and 2013.

Explanation / Answer

2012:

Contract price

$1,800,000

Actual costs to date

$450,000

Estimated costs to complete

1,200,000

Total estimated project costs

1,650,000

Estimated total gross profit

150,000

Percentage of completion:

   $450,000/ $1,650,000

27.27%

Gross profit recognized

$40,905

2013:

Contract price

$1,800,000

Costs incurred: 2012

$450,000

2013

1,100,000

Total cost

1,550,000

Total gross profit

250,000

Recognized in 2012

40,905

Recognized in 2013

$ 209,095

2012:

Contract price

$1,800,000

Actual costs to date

$450,000

Estimated costs to complete

1,200,000

Total estimated project costs

1,650,000

Estimated total gross profit

150,000

Percentage of completion:

   $450,000/ $1,650,000

27.27%

Gross profit recognized

$40,905

2013:

Contract price

$1,800,000

Costs incurred: 2012

$450,000

2013

1,100,000

Total cost

1,550,000

Total gross profit

250,000

Recognized in 2012

40,905

Recognized in 2013

$ 209,095