Heritage Gardens uses a job-order costing system to track the costs of its lands

ID: 2377571 • Letter: H

Question

Heritage Gardens uses a job-order costing system to track the costs of its landscaping projects. The company uses a job-order costing system to track the costs of its landscaping projects. The table below provides data concerning the three landscaping projects that were in progress during May. There was no work in process at the beginning of May.style="font-size: 12px;">style="font-size: 12px;">



Actual overhead costs were $16,000 for May. Overhead costs are applied to projects on the basis of designer- hours since most of the overhead is related to the costs of the garden design studio. The predetermined overhead rate is $45 per>style="font-size: 12px;">

designer- hour. The Williams and Chandler projects were completed in May; the Nguyen project was not completed by the end of the month. No other jobs were in process during May.style="font-size: 12px;">style="font-size: 12px;">style="font-size: 12px;">style="font-size: 12px;">


QUESTION 1 - Compute the amount of overhead cost that would have been applied to each project during May. Show your work.style="font-size: 12px;" data-mce-style="font-size: 12px;">style="font-size: 12px;" data-mce-style="font-size: 12px;">


style="font-size: 12px;" data-mce-style="font-size: 12px;">

QUESTION 2 - Determine the cost of goods manufactured for May.  Show your work.style="font-size: 12px;" data-mce-style="font-size: 12px;">


style="font-size: 12px;" data-mce-style="font-size: 12px;">

QUESTION 3 - What is the accumulated cost of the work in process at the end of the month? data-mce-style="font-size: 12px;"> data-mce-style="font-size: 12px;">Show your work.data-mce-style="font-size: 12px;">style="font-size: 12px;">


data-mce-style="font-size: 12px;">
style="font-size: 12px;">

QUESTION 4 - Determine the underapplied or overapplied overhead for May.  style="font-size: 12px;" data-mce-style="font-size: 12px;">Show your work.data-mce-style="font-size: 12px;">style="font-size: 12px;">

PROJECTS Williams Chandler Nguyen Designer Hours 200 80 120 Direct Materials $  4,800.00 $  1,800.00 $  3,600.00 Direct Labor $  2,400.00 $  1,000.00 $  1,500.00

Explanation / Answer

Overhead cost for may is overapplied:

Actual O/H applied = $16000

FOH is overapplied by (16000 - 18000 ) = $2000