Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

County over a three-year period (2013 through 2015). The contract price is $1,20

ID: 2379275 • Letter: C

Question

County over a three-year period (2013 through 2015). The contract

price is $1,200,000 and the construction costs (both actual and

estimated) total $705,000 for the three years. The percentage

completed at the end of each year is as follows: 2013, 20%; 2014,

75%; 2015, 100%.

Required

1. Prepare a schedule showing the amount of gross profit that Tarlo

Company recognizes each year using the percentage-of completion

method.

2. Prepare a schedule showing the amount of gross profit that Tarlo

Company recognizes each year using the completed contract

method.


Explanation / Answer


a) The percentage-of-completion method recognizes revenues, costs, and gross profit as progress is made toward

completion on a long-term contract.



b) Under the completed-contract method, revenue and gross profit are recognized only at point of sale, that is, when

the contract is completed. Costs of long-term contracts in process and current billings are accumulated, but there

are no interim charges or credits to income statement accounts for revenues, costs, and gross profit.




2013 2014 2015 Total % of Completion 20% 75% 100%
Contract Price $ 1,200,000 Construction Costs $ 705,000 Price on % of Completion Method $ 240,000 $ 660,000 $ 300,000 $ 1,200,000 Construction Costs % of Completion $ 141,000 $ 387,750 $ 176,250 $ 705,000 Gross Profit $ 99,000 $ 272,250 $ 123,750 $ 495,000