Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider two mutually exclusive projects with the following cash flows: Project

ID: 2383656 • Letter: C

Question

Consider two mutually exclusive projects with the following cash flows:

Project

C/F0

C/F1

C/F2

C/F3

C/F4

C/F5

C/F6

A

$(41,215)

$12,500

$14,000

$16,500

$18,000

20,000

N/A

B

$(46,775)

$15,000

$15,000

$15,000

$15,000

$15,000

$15,000

Assuming that the discount rate for project A is 16% and the discount rate for B is 15%, then given that these are mutually exclusive projects, which project would you take and why?

Project

C/F0

C/F1

C/F2

C/F3

C/F4

C/F5

C/F6

A

$(41,215)

$12,500

$14,000

$16,500

$18,000

20,000

N/A

B

$(46,775)

$15,000

$15,000

$15,000

$15,000

$15,000

$15,000

Explanation / Answer

Project A

NPV = -41215 + 12500/1.16 + 14000/1.16^2 + 16500/1.16^3 + 18000/1.16^4 + 20000/1.16^5

NPV = $ 9999.49

PVA(16%,5) = 3.274294

Equivalent Annual Benefit = NPV of Project A/PVA(16%,5)

Equivalent Annual Benefit  = 9999.49/3.274294

Equivalent Annual Benefit = $ 3053.94

Project B

PVA(15%,6) = 3.784483

NPV = -46775 + 15000*PVA(15%,6)

NPV = -46775 + 15000*3.784483

NPV = $ 9992.25

Equivalent Annual Benefit = NPV of Project B/PVA(15%,6)

Equivalent Annual Benefit = 9992.25/3.784483

Equivalent Annual Benefit = $ 2650.32

Decision : Project A should be selected as its Equivalent Annual Benefit is higher than Project B