Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

COSt P10-3A Ratchet Company flexible report for the company\'s Assembling Depart

ID: 2404649 • Letter: C

Question

COSt P10-3A Ratchet Company flexible report for the company's Assembling Departmentosts. The A uses budgets company's Assembling Department is as follows. RATCHET COMPANY Budget Report Assembling Department For the Month Ended August 31, 2017 Difference Favorable Unfavorable U Manufacturing Costs Variable costs Direct materials Direct labor Indirect materials Indirect labor Utilities Maintenance 1,000 F 2,800 F 200 U 500 F 100 F 400 U 48,000 $47,000 51,200 54,00024,200 24,000 18,000 15,000 12,000 17,500 14,900 12,400 167,200 171.000 167,.2003,800 F Total variable Fixed costs Rent Supervision Depreciation 12,000 17,000 6,000 35,000 12,000 17,000 6,000 35,000 $206,000 $202,200 Total fixed Total costs $3,800 F The monthly budget amounts in the report were based on an expected productiond 60,000 units per month or 720,000 units per year. The Assembling Department managers pleased with the report and expects a raise, or at least praise for a job well done. The con pany president, however, is unhappy with the results for August because only 58,000 t5 were produced. Instructions (a) State the total monthly budgeted cost formula. August using flexible budget data. Why does this report for evaluating performance than the report based on static bou budget report for provide a bette get data? report using Blexible actual cost in (c) In September, 64,000 units were produced. Prepare the budget data, assuming (1) each variable cost was 10% higher than its August, and (2) fixed costs were the same in September as in

Explanation / Answer

Answer:

Total budgeted fixed cost+(Budgeted variable cost/no.of budgeted units)

=$35000+$2.85 varible cost per unit

2. Flexible budget for August

Budgeted

actual

Difference

Favourable(F)/Un favourable(UF).

Units

58000

58000

Variable cost

D.Materials

46400

47000

-600

UF

D.Labour

52200

51200

1000

F

Indirect Material

23200

24200

-1000

UF

Indirect Labour

17400

17500

-100

UF

Utilities

14500

14900

-400

UF

Maitenance

11600

12400

-800

UF

Total Variable

165300

167200

-1900

UF

Fixed Cost

Rent

12000

12000

0

Supervision

17000

17000

0

Depreciation

6000

6000

0

Total Fixed Cost

35000

35000

0

Total Cost

200300

202200

-1900

UF

3.FLEXIBLE BUDGET IN SEPTEMBER MONTH IN CASE VARIABL COST INCREAE BY 10%

Budgeted

actual

Difference

Favourable(F)/Un favourable(UF).

Units

64000

64000

Variable cost

D.Materials

56320

57048

-728

UF

D.Labour

63360

62146

1214

F

Indirect Material

28160

29374

-1214

UF

Indirect Labour

21120

21241

-121

UF

Utilities

17600

18086

-486

UF

Maintenance

14080

15051

-971

UF

Total Variable

200640

202946

-2306

UF

Fixed Cost

Rent

12000

12000

0

Supervision

17000

17000

0

Depreciation

6000

6000

0

Total Fixed Cost

35000

35000

0

Total Cost

235640

237946

-2306

UF

Budgeted

actual

Difference

Favourable(F)/Un favourable(UF).

Units

58000

58000

Variable cost

D.Materials

46400

47000

-600

UF

D.Labour

52200

51200

1000

F

Indirect Material

23200

24200

-1000

UF

Indirect Labour

17400

17500

-100

UF

Utilities

14500

14900

-400

UF

Maitenance

11600

12400

-800

UF

Total Variable

165300

167200

-1900

UF

Fixed Cost

Rent

12000

12000

0

Supervision

17000

17000

0

Depreciation

6000

6000

0

Total Fixed Cost

35000

35000

0

Total Cost

200300

202200

-1900

UF