Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm f

ID: 2413773 • Letter: P

Question

Problem 16-3A (Part Level Submission) Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows. Cutting Department Plant 1 T12-Tables Plant2 C10-Chairs Production Data-July Work in process units, July 1 Units started into production Work in process units, July 31 Work in process percent complete 0 21,600 3,240 60 0 17,280 540 80 Cost Data-July Work in process, July 1 Materials Labor Overhead 410,400 253,152 112,320 $775,872 311,040 118,800 113,184 $543,024 Total (a1) Your answer is correct. For each plant compute the physical units of production. T12 Tables C10 Chairs 17280 Units to be accounted for 21600 Click if you would like to Show Work for this question: Open Show Work

Explanation / Answer

Answer

Reconciliation of Units

Opening WIP

0

Introduced

21600

TOTAL

21600

Transferred

18360

Closing WIP

3240

Statement of Equivalent Units

Material

Conversion Cost

Units

Complete %

Equivalent units

Complete %

Equivalent units

Transferred

18360

100%

18360

100%

18360

Closing WIP

3240

100%

3240

60%

1944

Total

21600

Total

21600

Total

20304

Cost per Equivalent Units

COST

Material cost

Conversion cost

TOTAL

Opening + Current cost

410400

365472

775872

Total Equivalent Units

21600

20304

Cost per Equivalent Units

$19.0000

$18.0000

$37.0000

Statement of cost

Cost

Cost/unit

Closing WIP

Transferred

Units

Cost Allocated

Units

Cost Allocated

Material

19.0000

3240

61560

18360

348840

Conversion cost

18.0000

1944

34992

18360

330480

Total

37.0000

TOTAL

$96552

TOTAL

$679320

Reconciliation of Units

Opening WIP

0

Introduced

17280

TOTAL

17280

Transferred

16740

Closing WIP

540

Statement of Equivalent Units

Material

Conversion Cost

Units

Complete %

Equivalent units

Complete %

Equivalent units

Transferred

16740

100%

16740

100%

16740

Closing WIP

540

100%

540

80%

432

Total

17280

Total

17280

Total

17172

Cost per Equivalent Units

COST

Material cost

Conversion cost

TOTAL

Opening + Current cost

311040

231984

543024

Total Equivalent Units

17280

17172

Cost per Equivalent Units

$18.0000

$13.5

$31.5

Statement of cost

Cost

Cost/unit

Closing WIP

Transferred

Units

Cost Allocated

Units

Cost Allocated

Material

18.0000

540

9720

16740

301320

Conversion cost

13.5

432

5832

16740

225990

Total

31.5

TOTAL

$15552

TOTAL

$527310

Cost accounted for----

T12 Tables

[18360 units x $37]

Transferred out

$ 6,79,320.00

Work In Process:

[3240 units x $19]

Materials

$ 61,560.00

[1944 units x $18]

Conversion Costs

$ 34,992.00

$      96,552.00

Total costs

$ 7,75,872.00

Cost accounted for----

C10 Chairs

[16740 units x $31.5]

Transferred out

$ 5,27,310.00

Work In Process:

[540 units x $18]

Materials

$    9,720.00

[432 units x $13.5]

Conversion Costs

$    5,832.00

$      15,552.00

Total costs

$ 5,42,862.00

Reconciliation of Units

Opening WIP

0

Introduced

21600

TOTAL

21600

Transferred

18360

Closing WIP

3240

Statement of Equivalent Units

Material

Conversion Cost

Units

Complete %

Equivalent units

Complete %

Equivalent units

Transferred

18360

100%

18360

100%

18360

Closing WIP

3240

100%

3240

60%

1944

Total

21600

Total

21600

Total

20304

Cost per Equivalent Units

COST

Material cost

Conversion cost

TOTAL

Opening + Current cost

410400

365472

775872

Total Equivalent Units

21600

20304

Cost per Equivalent Units

$19.0000

$18.0000

$37.0000

Statement of cost

Cost

Cost/unit

Closing WIP

Transferred

Units

Cost Allocated

Units

Cost Allocated

Material

19.0000

3240

61560

18360

348840

Conversion cost

18.0000

1944

34992

18360

330480

Total

37.0000

TOTAL

$96552

TOTAL

$679320