Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Indiana Co. began a construction project in 2011 that will provide it $150 milli

ID: 2452892 • Letter: I

Question

Indiana Co. began a construction project in 2011 that will provide it $150 million when it is completed in

2013. During 2011, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to

complete the project.

In 2012, Indiana incurred costs of $58.5 million and estimated an additional $40.5 million in costs to

complete the project. Using the percentage-of-completion method, Indiana recognized _______ on the

project in 2012.

A. $15 million gross profit

B. $6 million gross profit

C. $13.5 million gross profit

D. $1.5 million gross profit

Explanation / Answer

in 2011 Estmated profit on project=150-36-84=30

Profit recognised=30/120*36=9

In 2012 estmated profit on project=150-58.5-40.5-36=15

Profit to be recognised up to 2012=15/135*(58.5+36)=10.5

already recognised =9

so to be recognised in 2012 is 10.5-9=$1.5