Carbon Company provides the following information about resources: Unused Resources Capacity Cost Driver Volume Resources used Materials $ 2,000 8,000 pounds Energy 1,560 340 machine-hours Setups -0- 80 setups Purchasing 1,800 80 purchase orders Customer service 7,600 50 returns Long-term labor 3,400 320 labor-hours Administrative 2,800 420 labor-hours Resources supplied Materials $ 98,000 Energy 17,880 Setups 24,000 Purchasing 21,000 Customer service 15,600 Long-term labor 29,000 Administrative 28,000
Explanation / Answer
Answer:
Particulars Resources used Resource supplied Unused resources capacity Material 96000 98000 2000 Energy 16320 17880 1560 Setups 24000 24000 0 Purchasing 19200 21000 1800 Customer service 8000 15600 7600 Long-Term labor 25600 29000 3400 Administrative 25200 28000 2800