Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 16-3A (Part Level Submission) Cutting Department Production Data—July Pl

ID: 2534491 • Letter: P

Question

Problem 16-3A (Part Level Submission)

Cutting Department

Production Data—July

Plant 1
T12-Tables

Plant 2
C10-Chairs

Cost Data—July

(a)

T12 Tables

C10 Chairs

Materials

Conversion Costs

Materials

Conversion Costs

Total Costs

T12 Tables

Costs accounted for:

   Transferred out

   Work in process

      Materials

      Conversion costs

         Total costs

C10 Chairs

Costs accounted for:

   Transferred out

   Work in process

      Materials

      Conversion costs

         Total costs

Problem 16-3A (Part Level Submission)

Seagren Industries Inc. manufactures in separate processes furniture for homes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows.

Cutting Department

Production Data—July

Plant 1
T12-Tables

Plant 2
C10-Chairs

Work in process units, July 1 0 0 Units started into production 21,850 18,400 Work in process units, July 31 3,450 575 Work in process percent complete 60 80

Cost Data—July

Work in process, July 1 $0 $0 Materials 437,000 331,200 Labor 269,330 126,500 Overhead 119,600 111,205    Total $825,930 $568,905

Explanation / Answer

T12 table

C 10 chairs

Beggining units 0 Transferred out 18,400 Started intro production 21850 Ending units 3,450 Units accounted for 21850 21850 Equivalent units Material Conversion cost Units transferred                      A 18400 18400 Ending Units 3,450 3,450 Completion 100% 60% B 3450 2070 Total units 21850 20470 Cost per equivalent units Particulars Material Conversion cost total As at beginning 0 0 0 Added during the month 437000 388930 825930 Cost to be accounted for 437000 388930 825930 Total eqivalent units 21850 20470 Cost per equivalent unit 20.00 19.00 39.00 Cost per equivalent unit = Cost to be accounted for / Total equivalent units