Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Please show work for the following question: Seasons Construction is constructin

ID: 2551597 • Letter: P

Question

Please show work for the following question:

Seasons Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1,550,000 each quarter. The total contract price is $18,600,000 and Seasons estimates total costs of $17,750,000. Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2018, Seasons estimated that it was 30% complete with the construction, based on costs incurred.

At December 31, 2019, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $18,000,000 due to unanticipated price increases. What is reported in the balance sheet at December 31, 2019 for Seasons as the difference between the Construction in Process and the Billings on Construction in Process accounts, and is it a debit or a credit?

Difference between the accounts                     Debit/Credit

a $4,225,000                                        Credit

b $1,550,000                                       Debit

c $1,100,000                                      Debit

d $1,550,000                                       Credit

Explanation / Answer

At 31st December 2019, the Season Construction must have raised to bill of $ 12,400,000($1,550,000*8 quarters)

At 31st December 2019, Total cost incurred must be $ 13,500,000 ($18,000,000*75%)

There is excess of cost incurred as compare to billing done.

Hence we should report in the balance sheet at December 31, 2019 a debit balance of $ 1,100,000 ($13,500,000-$12,400,000)