CSMT 401 FALL 2017 Assignment- DUE November 7, 2017 BY 11:00AM Solve the followi

ID: 2565356 • Letter: C

Question

CSMT 401 FALL 2017 Assignment- DUE November 7, 2017 BY 11:00AM Solve the following based on lecture notes and text. Print the assignment then, solve on the printed pagests). Scan your completed assignment and upload to Blackboard no later than 11:00a. XYZ Company is building a small project in Montgomery, Alabama. The project consists of 12 activities. It takes one month to complete each activity. Below are the estimated costs and durations, as of today, for the 1· The project costs are estimated to be $257,000. The project is scheduled to be completed in six months. After three and a half months, the sitework, excavation, foundation, fencing, and rough electrical work are completed. costs to date are $152,000. What is the status of the project in terms of schedule and budget? HINT: You must calculate: Actual Cost of Work Performed (ACWP), Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), Schedule Variance (days), Schedule Variance (S), Cost Variance (%) Schedule Performance Index (SPI), Cost Performance Index (CPI), Percent Complete. 22000 $10,000 $18,000 30,000 $ s0,000 S40.000 6,000 encing Paving Excavation Framing ough electric Rough plumbing16,000 4,000 14,000 Drywall Suspend ceiling Interior finish

Explanation / Answer

Answer to Question No. 1) The budget is under control in terms of schedule as no major deviation has been noted from the schedule time of completion. The activities related to sitework, fencing, excavation, foundation and rough elctric is completed within the expected time frame. However, as per planning the paving activity should get completed by 3rd Month but the same is not done as per the planning schedule and results in major deviation. The deviation is of 15 days as the same needs to be completed by 3rd month and we are evaluating the project at 3 and half month.Further, the framing and rough electric work is scheduled to be completed by 4rth month and 50% and 75% of both the activities is respectively done after 3 and half month. We can estimate that the remaining 50% of framing activity and 25% of rough electric work will get completed by end of 4rth month. Thus, there are no deviations noted.

Activities Estimated Cost % of completion after 3 and half month Estimated Cost as per completion Sitework 22000 100% 22000 Fencing 10000 100% 10000 Paving 18000 50% 9000 Excavation 30000 100% 30000 Foundation 50000 100% 50000 Framing 40000 50% 20000 Rough Electric 6000 100% 6000 Rough Plumbing 16000 75% 12000 Drywall 13000 0% 0 Suspend Ceiling 4000 0% 0 Interior Finish 34000 0% 0 Carpeting 14000 0% 0 Total Estimated Cost 257000 159000 Total Estimated Cost for activity performed 159000 Total Cost Incurred to date 152000 Variance 7000 Positive The project cost variance is $7000 positive. This indicates that the estimated cost is more than the cost incurred means the company is performing in a favourable manner and is completing the projhect at minimum cost and within the estimated budget