Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cost Reduction Proposal: IRR, NPV, and Payback Period JB Chemical currently disc

ID: 2566609 • Letter: C

Question

Cost Reduction Proposal: IRR, NPV, and Payback Period JB Chemical currently discharges liquid waste into Calgary's municipal sewer system. However, the Calgary municipal government has informed JB that a surcharge of $4 per thousand cubic liters will soon be imposed for the discharge of this waste. This has prompted management to evaluate the desirability of treating its own liquid waste. A proposed system consists of three elements. The first is a retention basin, which would permit unusual discharges to be held and treated before entering the downstream system. The second is a continuous self-cleaning rotary filter required where solids are removed. The third is an automated neutralization process required where materials are added to control the alkalinity-acidity range. The system is designed to process 700,000 liters a day. However, management anticipates that only about 200,000 liters of liquid waste would be processed in a normal workday. The company operates 300 days per year. The initial investment in the system would be $360,000, and annual operating costs are predicted to be $150,000. The system has a predicted useful life of twelve years and a salvage value of $50,000. (a) Determine the project's net present value at a discount rate of 22 percent. (Round to the nearest whole number.) $ Answer (b) Determine the project's approximate internal rate of return. (Round your answer to the nearest whole percentage.) Answer % (c) Determine the project's payback period. Answer years

Explanation / Answer

Discount rate 22% Initial Cost          360,000 Salvage value            50,000 Life in years                    12 Liquid processed a day          200,000 liter No of days in year                  300 Total processed =200000*300    60,000,000 liter 1 Cubic liter=              1,000 liter Surcharge 4 per cubic liter Total surcharge =60000000*4/1000          240,000 This surcharge will be saved So annual saving          240,000 Annual cost          150,000 Net saving            90,000 Lets plot these cash flows below Year Cash flow PV Factor Present Value Cumulative cash flow 0       (360,000)         1.000         (360,000) (360,000) 1            90,000         0.820              73,770 (270,000) 2            90,000         0.672              60,468 (180,000) 3            90,000         0.551              49,564     (90,000) 4            90,000         0.451              40,626                 -   5            90,000         0.370              33,300        90,000 6            90,000         0.303              27,295     180,000 7            90,000         0.249              22,373     270,000 8            90,000         0.204              18,339     360,000 9            90,000         0.167              15,032     450,000 10            90,000         0.137              12,321     540,000 11            90,000         0.112              10,099     630,000 12            90,000         0.092                8,278     720,000 12            50,000         0.092                4,599     770,000 NPV              16,063 Net present value=            16,063 Payback period= 4 year calculation of IRR Year Cash flow PV Factor Present Value @ 22% PV Factor @ 30% Present Value @ 30% 0       (360,000)         1.000         (360,000)         1.000 (360,000) 1            90,000         0.820              73,770         0.769        69,231 2            90,000         0.672              60,468         0.592        53,254 3            90,000         0.551              49,564         0.455        40,965 4            90,000         0.451              40,626         0.350        31,512 5            90,000         0.370              33,300         0.269        24,240 6            90,000         0.303              27,295         0.207        18,646 7            90,000         0.249              22,373         0.159        14,343 8            90,000         0.204              18,339         0.123        11,033 9            90,000         0.167              15,032         0.094          8,487 10            90,000         0.137              12,321         0.073          6,528 11            90,000         0.112              10,099         0.056          5,022 12            90,000         0.092                8,278         0.043          3,863 12            50,000         0.092                4,599         0.043          2,146 NPV              16,063 NPV     (70,730) IRR =Lower rate + Difference in rates*(NPV at lower rate)/(Lower rate NPV-Higher rate NPV) IRR =22%+8%*(16063/(16063+70730)) 23.48% So the IRR from the project is 23.48%