Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 11-5A LINK TO TEXT LINK TO TEXT LINK TO TEXT LINK TO TEXT LINK TO TEXT L

ID: 2581352 • Letter: P

Question

Problem 11-5A

LINK TO TEXT

LINK TO TEXT

LINK TO TEXT

LINK TO TEXT

LINK TO TEXT

LINK TO TEXT

Problem 11-5A

Hart Labs, Inc. provides mad cow disease testing for both state and federal governmental agricultural agencies. Because the company’s customers are governmental agencies, prices are strictly regulated. Therefore, Hart Labs must constantly monitor and control its testing costs. Shown below are the standard costs for a typical test.
Direct materials (2 test tubes @ $1.20 per tube) $2.40 Direct labor (1 hour @ $30 per hour) 30.00 Variable overhead (1 hour @ $6.00 per hour) 6.00 Fixed overhead (1 hour @ $13.00 per hour) 13.00     Total standard cost per test $51.40
The lab does not maintain an inventory of test tubes. As a result, the tubes purchased each month are used that month. Actual activity for the month of November 2017, when 1,300 tests were conducted, resulted in the following:
Direct materials (2,678 test tubes) $2,812 Direct labor (1,352 hours) 37,856 Variable overhead 7,657 Fixed overhead 15,821
Monthly budgeted fixed overhead is $17,160. Revenues for the month were $88,400, and selling and administrative expenses were $4,200.

Explanation / Answer

Solution:

Part 1(a) --- Material Price Variance

Material Price Variance is the variance arises in the material cost due to difference in actual material purchase price from standard material price. Mathematically, it is calculated as below:

Material Price Variance = Actual Quantity (Standard Price – Actual Price)

Note --- Here actual quantity means actual quantity of material PURCHASED. If the question does not provide the information about material purchase, it is taken as equal to material consumed.

Direct Material Price Variance

Actual Price (AP) (2812 / 2678)

$1.05

per test tube

Standard Price (SP)

$1.20

per tube

Variance or Difference in Price

$0.15

per tube

x Actual Quantity PURCHASED

2678

tubes

Material Price Variance

$402

Favorable

Part 1 (b) ---- Material Quantity/Efficiency/Usage Variance

Material Efficiency (Usage) Variance measures variance in material cost due to usage/consumption of materials. It is calculated as below:

Material Quantity Variance = Standard Price (Standard Quantity for Actual Production – Actual Quantity USED)

Note --- Here actual quantity means actual quantity of material CONSUMED/USED

Direct Material Quantity Variance

Standard Quantity Allowed for actual production:

Actual Production/Activity

1300

tests

x Allowed Standard Quantity Per Unit

2

test tubes

Total Standard Quantity Allowed for actual production (SQAP)

2600

test tubes

Actual Quantity USED (AQU)

2678

test tubes

Variance or Difference in Quantity

78

test tubes

x Standard Price (SP)

$1.20

per pound

Material Quantity Variance

$94

Unfavorable

Part 1(c) Labor Rate/Price Variance

Labor Price Variance – It arises due to difference in actual rate paid from standard rate. It is calculated as below:

Labor Price Variance = Actual Time (Standard Rate per hour – Actual Rate per hour)

Here, actual time means time for which wage has been paid.

Labor Rate Variance

Actual Hourly Rate (AHR)

(Actual labor cost $37,856 / Number of hour worked 1352)

$28.00

Per Hour

Standard Hourly Rate (SHR)

$30.00

Per Hour

Variance or Difference in Rate

$2.00

Per Hour

x Actual Labor Hours worked

1352

Hours

Labor Rate Variance

$2,704

Favorable

Part1(d) Labor Efficiency / Usage Variance

Labor Efficiency Variance – It arises due to variation in the working hours from the set standard.

Labor Efficiency Variance = Standard Rate (Std. hours for actual production – Actual Hours)

Labor Efficiency Variance

Standard Hours Allowed for actual production:

Actual Production/Activity

1300

tests

x Allowed Standard Hours Per Unit

1

hours

Total Standard Hours Allowed for actual production (SHAP)

1300

hours

Actual Labor Hours Worked (AH)

1352

hours

Variance or Difference in Quantity (AH - SHAP)

52

hours

x Standard Hourly Rate (SHR)

$30

per hour

Labor Efficiency Variance

$1,560

Unfavorable

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Pls ask separate question for remaining parts.

Direct Material Price Variance

Actual Price (AP) (2812 / 2678)

$1.05

per test tube

Standard Price (SP)

$1.20

per tube

Variance or Difference in Price

$0.15

per tube

x Actual Quantity PURCHASED

2678

tubes

Material Price Variance

$402

Favorable