Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cost Reduction Proposal: IRR, NPV, and Payback Period JB Chemical currently disc

ID: 2584888 • Letter: C

Question

Cost Reduction Proposal:
IRR, NPV, and Payback Period
JB Chemical currently discharges liquid waste into Calgary's municipal sewer system. However, the Calgary municipal government has informed JB that a surcharge of $4 per thousand cubic liters will soon be imposed for the discharge of this waste. This has prompted management to evaluate the desirability of treating its own liquid waste.

A proposed system consists of three elements. The first is a retention basin, which would permit unusual discharges to be held and treated before entering the downstream system. The second is a continuous self-cleaning rotary filter required where solids are removed. The third is an automated neutralization process required where materials are added to control the alkalinity-acidity range.

The system is designed to process 500,000 liters a day. However, management anticipates that only about 200,000 liters of liquid waste would be processed in a normal workday. The company operates 300 days per year. The initial investment in the system would be $360,000, and annual operating costs are predicted to be $150,000. The system has a predicted useful life of twelve years and a salvage value of $40,000.

(a) Determine the project's net present value at a discount rate of 26 percent. (Round to the nearest whole number. Use a negative sign with your answer if appropriate.)
$ Answer

(b) Determine the project's approximate internal rate of return. (Round to the nearest whole percentage.)
Answer %

(c) Determine the project's payback period.
Answer years

Explanation / Answer

Saving of surcharge of discharge if proposed system is installed:

(200000/1000 * $ 4)

=

$800 per day

No. of days

=

300 days

Annual saving

(800 * 300)

=

$240,000

Annual operating cost

=

($150,000)

Net Savings Annually

=

$90,000

NPV for Proposed System

YEAR

VALUE

DISCOUNT VALUE @ 26%

PRESENT VALUE

Initial cost

0

-360000

1.0000

-360000

Net Savings Annually

1-12

90000

3.6059

324531

Salvage value

12th

40000

0.0625

2500

-32969

(a) Project's NPV is $-32969

(b) IRR is the discounting rate which will result in NPV zero. Here NPV is -32969 when discounting rate is 26%.

and NPV is 44016 when Discount rate is 20%. Using trial and error, we get IRR

IRR

23.15%

(c) Payback period

Since NPV is negative for 12 years @ 26% payback is for more than 12 years.

Hence, with the given life of proposed system and 26% discount rate, company

is not going to realize its initial investment in a period of 12 years.

Saving of surcharge of discharge if proposed system is installed:

(200000/1000 * $ 4)

=

$800 per day

No. of days

=

300 days

Annual saving

(800 * 300)

=

$240,000

Annual operating cost

=

($150,000)

Net Savings Annually

=

$90,000

NPV for Proposed System

YEAR

VALUE

DISCOUNT VALUE @ 26%

PRESENT VALUE

Initial cost

0

-360000

1.0000

-360000

Net Savings Annually

1-12

90000

3.6059

324531

Salvage value

12th

40000

0.0625

2500

-32969

(a) Project's NPV is $-32969

(b) IRR is the discounting rate which will result in NPV zero. Here NPV is -32969 when discounting rate is 26%.

and NPV is 44016 when Discount rate is 20%. Using trial and error, we get IRR

IRR

23.15%

(c) Payback period

Since NPV is negative for 12 years @ 26% payback is for more than 12 years.

Hence, with the given life of proposed system and 26% discount rate, company

is not going to realize its initial investment in a period of 12 years.