Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 7-1 Calculating Payback Period and NPV Tri Star, Inc., has the following

ID: 2658432 • Letter: P

Question






Problem 7-1 Calculating Payback Period and NPV Tri Star, Inc., has the following mutually exclusive projects earproject A Project 0 $13,600 $9,000 1 8,200 3,700 2 6,8003,200 3 2,100 5, 600 ped ook Calculate the payback period for each project. (Do not round interme erences lplaces, e.g., 32.16.) Payback Period Project years Project Based on the payback period, which project should the company accep O Project A O Project B If the appropriate discount rate is 15 percent, what is the NPV for each pre your answers to 2 decimal places, e.g., 32.16.) NPV Project A. Project

Explanation / Answer

1)

PROJECT A:

Cumulative cash flow for year 0 = -13600

Cumulative cash flow for year 1 = -13600 + 8200 = -5400

Cumulative cash flow for year 2 = -5400 + 6800 = 1,400

5400 / 6800 = 0.79

Payback period fpr project A = 1 + 0.79 = 1.79 years

PROJECT B:

Cumulative cash flow for year 0 = -9000

Cumulative cash flow for year 1 = -9000 + 3700 = -5300

Cumulative cash flow for year 2 = -5300 + 3200 = -2100

Cumulative cash flow for year 3 = -2100 + 5600 = 3500

2100 / 5600 = 0.375

Payback period for project B = 2 + 0.38 = 2.38 years

We will accept project A as it has a lower payback period.

2)

PROJECT A:

NPV = Present value of cash inflows - present value of cash outflows

NPV = -13600 + 8200 / ( 1 + 0.15)1 + 6800 / ( 1 + 0.15)2 + 2100 / ( 1 + 0.15)3

NPV = -13600 + 7130.4348 + 5141.7769 + 1380.7841

NPV = 52.99 or $53

PROJECT B:

NPV = Present value of cash inflows - present value of cash outflows

NPV = -9000 + 3700 / ( 1 + 0.15)1 + 3200 / ( 1 + 0.15)2 + 5600 / ( 1 + 0.15)3

NPV = -9000 + 3217.3913 + 2419.6597 + 3682.0909

NPV = 319.14

Based on NPV, Project B should be accepted as it has a higher NPV.