Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Maxwell Software, Inc., has the following mutually exclusive projects. Year Proj

ID: 2742434 • Letter: M

Question

Maxwell Software, Inc., has the following mutually exclusive projects. Year Project A Project B 0 –$32,000 –$35,000 1 18,000 19,000 2 14,500 13,000 3 4,100 14,500 Calculate the payback period for each project: Payback period Project A ___years Project B ___years Which, if either, of these projects should be chosen? Project A Project B Both projects Neither project What is the NPV for each project if the appropriate discount rate is 15 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) NPV Project A $_____   Project B $______ Which, if either, of these projects should be chosen if the appropriate discount rate is 15 percent? ______ Project A or _____ Project B or _____Both or _____projects Neither project

Explanation / Answer

Answer to Part a : Payback period

PROJECT A

Year

Cash Flow

Cumulative Cash Flow

Year 0

(32,000)

(32,000)

Year 1

18,000

18,000

Year 2

14,500

32,500

Year 3

4,100

36,600

Payback period = 1 + 14,000/14,500 * 12

Payback period = 1 year 11 month 17 days

PROJECT B

Year

Cash Flow

Cumulative Cash Flow

Year 0

(35,000)

(35,000)

Year 1

19,000

19,000

Year 2

13,000

32,000

Year 3

14,500

46,500

Payback period = 2 + 3,000/14,500 * 12

Payback period = 2 year 2 month 14 days

Answer to Part b

Maxwell Software Inc should select Project A, as the Project A has lower Payback period.

Answer to Part c

PROJECT A

Year

Cash Flow

PV factor

PV of Cash Flow

Year 0

(32,000)

1

(32,000)

Year 1

18,000

0.8696

15,652.80

Year 2

14,500

0.7561

10,963.45

Year 3

4,100

0.6575

2,695.75

Total

2,688

NPV of Project A= 2,688

PROJECT B

Year

Cash Flow

PV factor

PV of Cash Flow

Year 0

(35,000)

1

(35,000)

Year 1

19,000

0.8696

16,522.40

Year 2

13,000

0.7561

9,829.30

Year 3

14,500

0.6575

9,533.75

Total

885.45

NPV of Project B= 885.45

Answer to Part d:

As per NPV, Maxwell Software Inc should select Projct A, as Project A has a higher NPV.

Year

Cash Flow

Cumulative Cash Flow

Year 0

(32,000)

(32,000)

Year 1

18,000

18,000

Year 2

14,500

32,500

Year 3

4,100

36,600