Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the information about a project in the following tables: Task Predecess

ID: 2749697 • Letter: C

Question

Consider the information about a project in the following tables:

Task Predecessor Duration (days) Scheduled Cost/Day

A

-----

4

$1,000

B

-----

6

$1,000

C

A

6

$4,000

D

B

9

$2,000

(Assume 5 working days each week)

                           End of Week 1                                  End of Week 2

                 Actual % Cumulative Actual % Cumulative

Task       Completed Actual Cost Completed Actual Cost

A

50%

$3,000

100%

$5,000

B

40%

$4,000

100%

$8,000

C

0%

$0

80%

$25,000

D

0%

$0

60%

$10,000

Use the earned value approach to calculate all measures, indices and variances for each task and the whole project at the end of weeks 1 & 2.

Task Predecessor Duration (days) Scheduled Cost/Day

A

-----

4

$1,000

B

-----

6

$1,000

C

A

6

$4,000

D

B

9

$2,000

Explanation / Answer

The variance computations are as follows:

For the first week:

Task

Cost of task

% completed

Earned

Planned value

SV

A

3000

50%

1500

1000

500

B

4000

40%

1600

1000

600

C

0

0%

0

4000

0

D

0

0%

0

2000

0

Schedule variance = Earned – Planned

For the second week:

Task

Cost of task

% completed

Earned

Planned value

SV

A

5000

100%

5000

5000

0

B

8000

100%

8000

5000

3000

C

25000

80%

20000

20000

0

D

10000

60%

6000

10000

-4000

Task

Cost of task

% completed

Earned

Planned value

SV

A

3000

50%

1500

1000

500

B

4000

40%

1600

1000

600

C

0

0%

0

4000

0

D

0

0%

0

2000

0