Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Problem 13-1 NPV with Normal Cash Flows (LG13-3) Compute the NPV for Project M i

ID: 2795094 • Letter: P

Question

Problem 13-1 NPV with Normal Cash Flows (LG13-3)

Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

NPV =

Problem 13-2 NPV with Normal Cash Flows (LG13-3)

Compute the NPV statistic for Project Y if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

NPV =

Project M Time: 0 1 2 3 4 5 Cash flow: –$2,100 $570 $700 $740 $820 $320

Explanation / Answer

Statement showing Cash flows Project M Particulars Time PVf 9% Amount PV Cash Outflows                             -                          1.00                 (2,100.00)              (2,100.00) PV of Cash outflows = PVCO              (2,100.00) Cash inflows                         1.00                    0.9174                       570.00                    522.94 Cash inflows                         2.00                    0.8417                       700.00                    589.18 Cash inflows                         3.00                    0.7722                       740.00                    571.42 Cash inflows                         4.00                    0.7084                       820.00                    580.91 Cash inflows                         5.00                    0.6499                       320.00                    207.98 PV of Cash Inflows =PVCI                2,472.41 NPV= PVCI - PVCO                    372.41 Statement showing Cash flows Project Y Particulars Time PVf 10% Amount PV Cash Outflows                             -                          1.00                 (8,500.00)              (8,500.00) PV of Cash outflows = PVCO              (8,500.00) Cash inflows                         1.00                    0.9091                    3,730.00                3,390.91 Cash inflows                         2.00                    0.8264                    4,560.00                3,768.60 Cash inflows                         3.00                    0.7513                    1,900.00                1,427.50 Cash inflows                         4.00                    0.6830                       680.00                    464.45 PV of Cash Inflows =PVCI                9,051.45 NPV= PVCI - PVCO                    551.45