Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider the manufacturing process at Wonder Shed Inc., a manufacturer of storag

ID: 3176551 • Letter: C

Question

Consider the manufacturing process at Wonder Shed Inc., a manufacturer of storage sheds. The manufacturing process involves the procurement of sheets of steel that will be used to form both the roof and the base of each shed. A list of activities fabricate a roof, fabricate a base, and assemble a shed is shown in Table 4.1 below:

Punch the base

We use a beta distribution to represent an activity duration in minutes. We assume that the activity durations are independent. We denote the optimistic, the most likely and the pessimistic times by a, m and b. The mean time and the variance of each activity duration are calculated as follows.

Activity

a

m

b

Mean

Variance

1

15

20

30

20.83333

6.25

2

25

35

40

34.16667

6.25

3

20

25

30

25

2.777778

4

5

10

20

10.83333

6.25

5

10

20

25

19.16667

6.25

6

25

30

40

30.83333

6.25

7

10

15

30

16.66667

11.11111

8

35

40

60

42.5

17.36111

a.

The process contains two paths:

Path 1 : Start 1 3 5 7 8 End

Path 2 : Start 1 2 4 6 7 8 End

The longer path in the mean time is Path 2. By Central Limit Theorem, we assume that the duration of Path 2 is normally distributed. What is the probability that the duration of Path 2 does not exceed 170 minutes?

P(X1<170)=

b. Assume that the durations of Path 1 and Path 2 are independent (even though this assumption does not seem to be so reasonable.) What is the probability that both of Path 1 and Path 2 are done within 150 minutes.  

P(X1<150 and X2<150)=

Activity 1 Separate the roof and base materials 2

Punch the base

3 Punch the roof 4 Form the base 5 form the roof 6 Subassemble the base 7 Assemble 8 Inspect

Explanation / Answer

Using given data the duration of path 2 is 155.83 i.e. mean = 155.83

Variance of path 2 = 53.47

std. dev. = 7.31

P(X1 < 170) = P(z < (170-155.83)/(53.47)) = P(z < 0.265) = 0.9737

P(X1<150 and X2<150) = P(X2 < 150) as P2 is the critical path. If P2 is completed in 150 minutes P1 will be completed in same time.

P(X2 < 150) = P(z < (150-155.83)/(53.47)) = P(z < -0.1090) = 0.2126

Mean Variance Std. dev. Path 1 1-3-5-7-8 124.1667 43.75 6.614378 Path 2 1-2-4-6-7-8 155.8333 53.47222 7.31247